      "slug": "meta-el-paso-data-center-tx",
      "name": "Meta El Paso data center",
      "summary": "Meta's El Paso Data Center in El Paso, Texas, which broke ground in 2025.",
      "state": "TX",
      "city": "El Paso",
      "county": "El Paso County",
      "status": "under_construction",
      "developer": "Meta",
      "capacity_mw": null,
      "latitude": null,
      "longitude": null,
      "location_precision": null,
      "location_source": null,
      "location_verified_at": null,
      "published": "2026-09-08",
      "last_verified": "2026-09-08",
      "record_url": "https://datacenterrecord.org/projects/meta-el-paso-data-center-tx",
      "sources": [
        {
          "title": "Big things are happening, El Paso!",
          "url": "https://datacenters.atmeta.com/2026/03/big-things-are-happening-el-paso/",
          "publisher": "Meta Data Centers",
          "date": "2026-03-26",
          "source_tier": 1
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "under_construction",
          "effective_at": "2026-03-26",
          "date_basis": "content",
          "planned": false,
          "source_date": null,
          "summary": "Meta plans to add enough clean and renewable energy to match 100 percent of the electricity use of El Paso data center",
          "source_url": "https://datacenters.atmeta.com/2026/03/big-things-are-happening-el-paso/",
          "source_tier": 1
        },
        {
          "status": "under_construction",
          "effective_at": "2026-03-26",
          "date_basis": "content",
          "planned": false,
          "source_date": null,
          "summary": "Meta announced a $500,000 grant to support workforce development in partnership with El Paso public schools",
          "source_url": "https://datacenters.atmeta.com/2026/03/big-things-are-happening-el-paso/",
          "source_tier": 1
        },
        {
          "status": "under_construction",
          "effective_at": "2026-03-26",
          "date_basis": "content",
          "planned": false,
          "source_date": null,
          "summary": "Meta broke ground on El Paso Data Center last year (2025)",
          "source_url": "https://datacenters.atmeta.com/2026/03/big-things-are-happening-el-paso/",
          "source_tier": 1
        },
        {
          "status": "under_construction",
          "effective_at": "2026-03-26",
          "date_basis": "content",
          "planned": false,
          "source_date": null,
          "summary": "Meta El Paso Data Center will grow to 1 gigawatt",
          "source_url": "https://datacenters.atmeta.com/2026/03/big-things-are-happening-el-paso/",
          "source_tier": 1
        }
      ]
    }
  ]
}