  "license": "CC BY 4.0",
  "license_url": "https://creativecommons.org/licenses/by/4.0/",
  "attribution": "Data: Data Center Record, datacenterrecord.org, CC BY 4.0. Link to the specific record page where possible.",
  "source": "https://datacenterrecord.org/states/tx/collin-county",
  "retrieved_at": "2026-10-07T17:49:59.207Z",
  "count": 5,
  "projects": [
    {
      "slug": "prosper-data-center-500m-tx",
      "name": "Prosper data center ($500M)",
      "summary": "A $500 million data center project in Prosper had its rezoning request unanimously denied by the Planning and Zoning Commission, though the project may not be dead.",
      "state": "TX",
      "city": "Prosper",
      "county": "Collin County",
      "status": "cancelled",
      "developer": null,
      "capacity_mw": null,
      "latitude": 33.2,
      "longitude": -96.63333,
      "location_precision": "county",
      "location_source": "County seat (McKinney), Wikidata, placed at county level",
      "location_verified_at": "2026-09-16",
      "coordinate_source": "wikidata county seat",
      "location_last_verified": "2026-09-16",
      "site_address": null,
      "site_address_source_url": null,
      "published": "2026-09-04",
      "last_verified": "2026-09-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": 37.3,
      "site_acres_disclosed_as": "third_party_estimate",
      "site_acres_source_url": "https://constructionreviewonline.com/prosper-commission-recommends-denial-for-580m-project-tomahawk-data-center-in-texas/",
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "record_url": "https://datacenterrecord.org/projects/prosper-data-center-500m-tx",
      "sources": [
        {
          "title": "Developer withdraws proposed $580M data center plan in Prosper - Audacy",
          "url": "https://www.audacy.com/krld/news/local/developer-withdraws-proposed-580m-data-center-plan-in-prosper",
          "publisher": "Audacy",
          "date": "2026-09-09",
          "source_tier": 4
        },
        {
          "title": "Developer scrapes data center plan for Prosper, Texas",
          "url": "https://www.youtube.com/watch?v=Gce8bnqpxWc",
          "publisher": "YouTube",
          "date": "2026-09-08",
          "source_tier": 1
        },
        {
          "title": "Prosper Commission Recommends Denial for $580M Project Tomahawk Data Center in Texas",
          "url": "https://constructionreviewonline.com/prosper-commission-recommends-denial-for-580m-project-tomahawk-data-center-in-texas/",
          "publisher": "constructionreviewonline.com",
          "date": "2026-09-01",
          "source_tier": 4
        },
        {
          "title": "White Rose spikes $500M Prosper data center proposal after elected official pushback - The Real Deal",
          "url": "https://therealdeal.com/texas/2026/09/09/white-rose-spikes-data-center-proposal-in-prosper/",
          "publisher": "The Real Deal",
          "date": "2026-09-09",
          "source_tier": 1
        },
        {
          "title": "Prosper P&Z votes against $500 million data center but project may not be dead - The Business Journals",
          "url": "https://www.bizjournals.com/dallas/news/2026/09/04/prosper-data-center-white-rose-denial.html",
          "publisher": "The Business Journals",
          "date": "2026-09-04",
          "source_tier": 4
        },
        {
          "title": "Prosper Planning and Zoning Commission unanimously denies controversial data center rezoning request - wfaa.com",
          "url": "https://www.wfaa.com/article/news/local/collin-county/prosper-planning-zoning-commission-denies-controversial-data-center-rezoning-request/287-e449e7f8-4e36-4cf2-b478-9ae99ceda139",
          "publisher": "wfaa.com",
          "date": "2026-09-02",
          "source_tier": 4
        },
        {
          "title": "Developer behind proposed \"Project Tomahawk\" data center in North Texas town withdraws - CBS News",
          "url": "https://www.cbsnews.com/texas/news/prosper-tx-project-tomahawk-pulled-9-8-2026/",
          "publisher": "CBS News",
          "date": "2026-09-08",
          "source_tier": 4
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "cancelled",
          "effective_at": "2026-09-09",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-09",
          "summary": "White Rose Partners withdrew $580 million Prosper data center proposal due to intense community opposition and zoning rejection",
          "source_url": "https://www.audacy.com/krld/news/local/developer-withdraws-proposed-580m-data-center-plan-in-prosper",
          "source_tier": 4
        }
      ]
    },
    {
      "slug": "aligned-data-centers-plano-tx",
      "name": "Aligned Data Centers Plano",
      "summary": "Aligned Data Centers lists 3 data centers at Plano, Texas among the sites it operates.",
      "state": "TX",
      "city": "Plano",
      "county": "Collin County",
      "status": "operational",
      "developer": "Aligned Data Centers",
      "capacity_mw": null,
      "latitude": 33.0502419,
      "longitude": -96.748682,
      "location_precision": "city",
      "location_source": "U.S. Census Bureau TIGERweb city centroid, public domain",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "tigerweb city centroid",
      "location_last_verified": "2026-09-14",
      "site_address": null,
      "site_address_source_url": null,
      "published": "2026-09-14",
      "last_verified": "2026-09-17",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "record_url": "https://datacenterrecord.org/projects/aligned-data-centers-plano-tx",
      "sources": [
        {
          "title": "Aligned Data Centers: Data center locations",
          "url": "https://aligneddc.com/locations/",
          "publisher": "Aligned Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "Aligned Data Centers: Aligned DFW-01",
          "url": "https://aligneddc.com/dallas-data-centers/",
          "publisher": "Aligned Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "BlackRock Reportedly In Talks To Buy Aligned Data Centers For $40B - Bisnow",
          "url": "https://www.bisnow.com/news/national/data-center-capital-markets/blackrock-in-advanced-talks-to-buy-aligned-data-centers-in-40b-deal-131227",
          "publisher": "Bisnow",
          "date": "2025-10-03",
          "source_tier": 1
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Aligned Data Centers lists Aligned DFW-01, Aligned DFW-02, Aligned DFW-04 at Plano, Texas on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://aligneddc.com/dallas-data-centers/",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "cyrusone-allen-dfw3-dfw5-tx",
      "name": "CyrusOne Allen DFW3-DFW5",
      "summary": "CyrusOne lists a data center at Allen, Texas among the sites it operates.",
      "state": "TX",
      "city": "Allen",
      "county": "Collin County",
      "status": "rumored",
      "developer": "CyrusOne",
      "capacity_mw": null,
      "latitude": 33.108757,
      "longitude": -96.6735544,
      "location_precision": "city",
      "location_source": "U.S. Census Bureau TIGERweb city centroid, public domain",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "tigerweb city centroid",
      "location_last_verified": "2026-09-14",
      "site_address": null,
      "site_address_source_url": null,
      "published": "2026-09-14",
      "last_verified": "2026-09-17",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "record_url": "https://datacenterrecord.org/projects/cyrusone-allen-dfw3-dfw5-tx",
      "sources": [
        {
          "title": "CyrusOne: Data centers",
          "url": "https://www.cyrusone.com/data-centers",
          "publisher": "CyrusOne",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "CyrusOne: CyrusOne Allen DFW3-DFW5",
          "url": "https://www.cyrusone.com/data-centers/north-america/allen-texas",
          "publisher": "CyrusOne",
          "date": "2026-09-14",
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": []
    },
    {
      "slug": "equinix-da7-plano-tx",
      "name": "Equinix DA7",
      "summary": "Equinix lists a data center at Plano, Texas among the sites it operates.",
      "state": "TX",
      "city": "Plano",
      "county": "Collin County",
      "status": "operational",
      "developer": "Equinix",
      "capacity_mw": null,
      "latitude": 33.0502419,
      "longitude": -96.748682,
      "location_precision": "city",
      "location_source": "U.S. Census Bureau TIGERweb city centroid, public domain",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "tigerweb city centroid",
      "location_last_verified": "2026-09-14",
      "site_address": null,
      "site_address_source_url": null,
      "published": "2026-09-14",
      "last_verified": "2026-09-17",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "record_url": "https://datacenterrecord.org/projects/equinix-da7-plano-tx",
      "sources": [
        {
          "title": "Equinix: United States and Canada colocation data centers",
          "url": "https://www.equinix.com/data-centers/americas-colocation/united-states-colocation",
          "publisher": "Equinix",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "Equinix: Equinix DA7",
          "url": "https://www.equinix.com/data-centers/americas-colocation/united-states-colocation/dallas-data-centers/da7",
          "publisher": "Equinix",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "MEDIA ALERT: Equinix to Host Launch Event at New Dallas Metro Data Center - PR Newswire",
          "url": "https://www.prnewswire.com/news-releases/media-alert-equinix-to-host-launch-event-at-new-dallas-metro-data-center-300232284.html",
          "publisher": "PR Newswire",
          "date": "2016-03-08",
          "source_tier": 1
        },
        {
          "title": "Equinix to unveil new $20 M data center in Legacy Business Park - The Business Journals",
          "url": "https://www.bizjournals.com/dallas/news/2016/03/10/equinix-to-unveil-new-20m-data-center-inlegacy.html",
          "publisher": "The Business Journals",
          "date": "2016-03-10",
          "source_tier": 1
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Equinix lists Equinix DA7 at Plano, Texas on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://www.equinix.com/data-centers/americas-colocation/united-states-colocation/dallas-data-centers/da7",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "stack-dfw01-plano-tx",
      "name": "STACK DFW01",
      "summary": "STACK Infrastructure lists a data center at Plano, Texas among the sites it operates.",
      "state": "TX",
      "city": "Plano",
      "county": "Collin County",
      "status": "operational",
      "developer": "STACK Infrastructure",
      "capacity_mw": null,
      "latitude": 33.0502419,
      "longitude": -96.748682,
      "location_precision": "city",
      "location_source": "U.S. Census Bureau TIGERweb city centroid, public domain",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "tigerweb city centroid",
      "location_last_verified": "2026-09-14",
      "site_address": null,
      "site_address_source_url": null,
      "published": "2026-09-14",
      "last_verified": "2026-09-17",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "record_url": "https://datacenterrecord.org/projects/stack-dfw01-plano-tx",
      "sources": [
        {
          "title": "STACK Infrastructure: Americas locations",
          "url": "https://www.stackinfra.com/locations/",
          "publisher": "STACK Infrastructure",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "STACK Infrastructure: STACK DFW01",
          "url": "https://www.stackinfra.com/locations/americas/dallas-fort-worth/",
          "publisher": "STACK Infrastructure",
          "date": "2026-09-14",
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "STACK Infrastructure lists STACK DFW01 at Plano, Texas on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://www.stackinfra.com/locations/americas/dallas-fort-worth/",
          "source_tier": 2
        }
      ]
    }
  ]
}