  "projects": [
    {
      "slug": "aligned-pit-01-shippingport-pa",
      "name": "Aligned PIT-01",
      "summary": "Aligned Data Centers lists a data center at Shippingport, Pennsylvania among the sites it operates.",
      "state": "PA",
      "city": "Shippingport",
      "county": "Beaver County",
      "status": "under_construction",
      "developer": "Aligned Data Centers",
      "capacity_mw": 2000,
      "latitude": 40.6261001,
      "longitude": -80.4205018,
      "location_precision": "city",
      "location_source": "U.S. Census Bureau TIGERweb city centroid, public domain",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "tigerweb city centroid",
      "location_last_verified": "2026-09-14",
      "site_address": null,
      "site_address_source_url": null,
      "published": "2026-09-14",
      "last_verified": "2026-09-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": "natural gas fuel cells (Bloom Energy)",
      "power_source_url": "https://stocktwits.com/news-articles/markets/equity/bloom-energy-gains-another-meaningful-proof-point-with-project-phoenix-says-rbc-2-gw-build-reinforces-data-center-opportunity/cZtnKFhRBcp",
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "record_url": "https://datacenterrecord.org/projects/aligned-pit-01-shippingport-pa",
      "sources": [
        {
          "title": "New data center complex breaks ground in Shippingport - Beaver County Times",
          "url": "https://www.timesonline.com/story/business/2026/09/13/first-data-center-project-in-beaver-county-pa-breaks-ground/91751558007/",
          "publisher": "Beaver County Times",
          "date": "2026-09-13",
          "source_tier": 4
        },
        {
          "title": "Ground broken on a Rust Belt powerhouse: Shippingport’s data hub rises in the Age of AI Anxiety - Washington Examiner",
          "url": "https://www.washingtonexaminer.com/opinion/columnists/4729194/ground-broken-rust-belt-powerhouse-pennsylvania-data-hub-ai-anxiety/",
          "publisher": "Washington Examiner",
          "date": "2026-09-16",
          "source_tier": 4
        },
        {
          "title": "Groundbreaking held for \"The Project Phoenix\" data center complex in Shippingport - Beaver County Radio",
          "url": "https://beavercountyradio.com/news/groundbreaking-held-for-the-project-phoenix-data-center-complex-in-shippingport/",
          "publisher": "Beaver County Radio",
          "date": "2026-09-14",
          "source_tier": 4
        },
        {
          "title": "Aligned Data Centers: Data center locations",
          "url": "https://aligneddc.com/locations/",
          "publisher": "Aligned Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "Aligned Data Centers: Aligned PIT-01",
          "url": "https://aligneddc.com/pennsylvania-data-centers/",
          "publisher": "Aligned Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "Aligned breaks ground on gigawatt scale data center campus in Pennsylvania - datacenterdynamics.com",
          "url": "https://www.datacenterdynamics.com/en/news/aligned-breaks-ground-on-gigawatt-scale-data-center-campus-in-pennsylvania/",
          "publisher": "datacenterdynamics.com",
          "date": "2026-09-17",
          "source_tier": 3
        },
        {
          "title": "Bloom Energy Gains Another ‘Meaningful’ Proof Point With Project Phoenix, Says RBC , 2 GW Build Reinforces Data Center Opportunity - Stocktwits",
          "url": "https://stocktwits.com/news-articles/markets/equity/bloom-energy-gains-another-meaningful-proof-point-with-project-phoenix-says-rbc-2-gw-build-reinforces-data-center-opportunity/cZtnKFhRBcp",
          "publisher": "Stocktwits",
          "date": "2026-09-15",
          "source_tier": 4
        },
        {
          "title": "New data center complex breaks ground in Beaver County - The Keystone Newsroom",
          "url": "https://keystonenewsroom.com/news/infrastructure/new-data-center-complex-breaks-ground-in-beaver-county/",
          "publisher": "The Keystone Newsroom",
          "date": "2026-09-14",
          "source_tier": 4
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "under_construction",
          "effective_at": "2026-09-17",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-17",
          "summary": "Aligned breaks ground on Project Phoenix data center campus in Shippingport",
          "source_url": "https://www.datacenterdynamics.com/en/news/aligned-breaks-ground-on-gigawatt-scale-data-center-campus-in-pennsylvania/",
          "source_tier": 3
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-17",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-17",
          "summary": "Project Phoenix is a 2GW data center campus with three facilities",
          "source_url": "https://www.datacenterdynamics.com/en/news/aligned-breaks-ground-on-gigawatt-scale-data-center-campus-in-pennsylvania/",
          "source_tier": 3
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-17",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-17",
          "summary": "Project Phoenix will use dedicated on site power source rather than local electrical grid",
          "source_url": "https://www.datacenterdynamics.com/en/news/aligned-breaks-ground-on-gigawatt-scale-data-center-campus-in-pennsylvania/",
          "source_tier": 3
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-17",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-17",
          "summary": "Project Phoenix site is located in Shippingport Industrial Park, Beaver County, 30 miles northwest of Pittsburgh",
          "source_url": "https://www.datacenterdynamics.com/en/news/aligned-breaks-ground-on-gigawatt-scale-data-center-campus-in-pennsylvania/",
          "source_tier": 3
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-17",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-17",
          "summary": "Shippingport Industrial Park site is adjacent to Shippingport Power Station, a former coal power plant being redeveloped into natural gas energy campus",
          "source_url": "https://www.datacenterdynamics.com/en/news/aligned-breaks-ground-on-gigawatt-scale-data-center-campus-in-pennsylvania/",
          "source_tier": 3
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-16",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-16",
          "summary": "On site natural gas power generation will feed the servers and eventually send surplus electricity back to PJM grid",
          "source_url": "https://www.washingtonexaminer.com/opinion/columnists/4729194/ground-broken-rust-belt-powerhouse-pennsylvania-data-hub-ai-anxiety/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-16",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-16",
          "summary": "Project Phoenix broke ground as a three facility, 2 gigawatt campus",
          "source_url": "https://www.washingtonexaminer.com/opinion/columnists/4729194/ground-broken-rust-belt-powerhouse-pennsylvania-data-hub-ai-anxiety/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-16",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-16",
          "summary": "Project Phoenix site is 660 acres on the former Bruce Mansfield coal plant footprint",
          "source_url": "https://www.washingtonexaminer.com/opinion/columnists/4729194/ground-broken-rust-belt-powerhouse-pennsylvania-data-hub-ai-anxiety/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-15",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-15",
          "summary": "Project Phoenix is a 2 GW three facility campus in Pennsylvania that has broken ground.",
          "source_url": "https://stocktwits.com/news-articles/markets/equity/bloom-energy-gains-another-meaningful-proof-point-with-project-phoenix-says-rbc-2-gw-build-reinforces-data-center-opportunity/cZtnKFhRBcp",
          "source_tier": 4
        },
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Aligned Data Centers lists Aligned PIT-01 at Shippingport, Pennsylvania on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://aligneddc.com/pennsylvania-data-centers/",
          "source_tier": 2
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-14",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Groundbreaking held for Project Phoenix data center complex in Shippingport",
          "source_url": "https://beavercountyradio.com/news/groundbreaking-held-for-the-project-phoenix-data-center-complex-in-shippingport/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-14",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Project Phoenix built on former Bruce Mansfield coal fired power plant site",
          "source_url": "https://beavercountyradio.com/news/groundbreaking-held-for-the-project-phoenix-data-center-complex-in-shippingport/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-14",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Project Phoenix features closed loop cooling system that requires no water for operational cooling",
          "source_url": "https://beavercountyradio.com/news/groundbreaking-held-for-the-project-phoenix-data-center-complex-in-shippingport/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-14",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Groundbreaking held September 10 for Project Phoenix data center campus",
          "source_url": "https://keystonenewsroom.com/news/infrastructure/new-data-center-complex-breaks-ground-in-beaver-county/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-14",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Three building campus featuring closed loop cooling system requiring zero water for operational cooling",
          "source_url": "https://keystonenewsroom.com/news/infrastructure/new-data-center-complex-breaks-ground-in-beaver-county/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-14",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Project Phoenix built on former Bruce Mansfield coal fired power plant site in Shippingport Industrial Park",
          "source_url": "https://keystonenewsroom.com/news/infrastructure/new-data-center-complex-breaks-ground-in-beaver-county/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-13",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-13",
          "summary": "Facility features closed loop cooling system requiring zero water for operational cooling",
          "source_url": "https://www.timesonline.com/story/business/2026/09/13/first-data-center-project-in-beaver-county-pa-breaks-ground/91751558007/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-13",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-13",
          "summary": "Groundbreaking held September 10 for Project Phoenix data center complex in Shippingport",
          "source_url": "https://www.timesonline.com/story/business/2026/09/13/first-data-center-project-in-beaver-county-pa-breaks-ground/91751558007/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-13",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-13",
          "summary": "Project Phoenix is a 2 GW data center campus in Shippingport",
          "source_url": "https://www.timesonline.com/story/business/2026/09/13/first-data-center-project-in-beaver-county-pa-breaks-ground/91751558007/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-13",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-13",
          "summary": "Three building campus built on former Bruce Mansfield coal fired power plant site in Shippingport Industrial Park",
          "source_url": "https://www.timesonline.com/story/business/2026/09/13/first-data-center-project-in-beaver-county-pa-breaks-ground/91751558007/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-09-13",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-13",
          "summary": "Project Phoenix will utilize dedicated onsite power source versus local electrical grid",
          "source_url": "https://www.timesonline.com/story/business/2026/09/13/first-data-center-project-in-beaver-county-pa-breaks-ground/91751558007/",
          "source_tier": 4
        }
      ]
    }
  ]
}