  "projects": [
    {
      "slug": "edged-mesa-data-center-az",
      "name": "Edged Mesa data center",
      "summary": "Edged operates its 36 MW Edged Phoenix (PHX01) data center at 8927 E Ray Rd in Mesa, Maricopa County, Arizona, using a waterless closed loop cooling system.",
      "state": "AZ",
      "city": "Mesa",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Edged",
      "capacity_mw": 36,
      "latitude": 33.321,
      "longitude": -111.6385,
      "location_precision": "address",
      "location_source": "Edged Phoenix (PHX01) facility specification page at 8927 E Ray Rd, Mesa, Maricopa County, Arizona.",
      "location_verified_at": "2026-09-23",
      "coordinate_source": "operator address point",
      "location_last_verified": "2026-09-23",
      "site_address": "8927 E Ray Rd, Mesa, AZ 85212",
      "site_address_source_url": "https://edged.us/phoenix",
      "published": "2026-09-08",
      "last_verified": "2026-10-26",
      "cooling_type": "closed_loop_liquid",
      "cooling_type_source_url": "https://edged.us/phoenix",
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 1,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://edged.us/phoenix",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/edged-mesa-data-center-az",
      "sources": [
        {
          "title": "Edged breaks ground on data center in Phoenix, Arizona - Data Center Dynamics",
          "url": "https://www.datacenterdynamics.com/en/news/edged-breaks-ground-on-data-center-in-phoenix-arizona/",
          "publisher": "Data Center Dynamics",
          "date": "2024-08-16",
          "source_tier": 1
        },
        {
          "title": "Growing Data Center Developer Plans New Project In Phoenix Area - Bisnow",
          "url": "https://www.bisnow.com/news/national/data-center/edged-energy-planning-phoenix-area-data-center-119836",
          "publisher": "Bisnow",
          "date": "2023-07-17",
          "source_tier": 1
        },
        {
          "title": "Edged US opens waterless AI data centre in Mesa, Arizona",
          "url": "https://datacenter.news/story/edged-us-opens-waterless-ai-data-centre-in-mesa-arizona",
          "publisher": "datacenter.news",
          "date": "2026-04-07",
          "source_tier": 4
        },
        {
          "title": "Edged US: Edged Phoenix (8927 E Ray Rd, Mesa, AZ) Facility Specifications",
          "url": "https://edged.us/phoenix",
          "publisher": "Edged",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-04-07",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Edged US opened a waterless AI data center in Mesa, Arizona",
          "source_url": "https://datacenter.news/story/edged-us-opens-waterless-ai-data-centre-in-mesa-arizona",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2024-08-16",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Edged Energy broke ground on a 36 MW, 210,000 sq ft high density AI data center in Mesa, Arizona, expected to come online in late 2025, powered by Salt River Project.",
          "source_url": "https://www.datacenterdynamics.com/en/news/edged-breaks-ground-on-data-center-in-phoenix-arizona/",
          "source_tier": 1
        }
      ]
    },
    {
      "slug": "vantage-phoenix-az",
      "name": "Vantage Phoenix (Goodyear AZ1)",
      "summary": "Vantage Data Centers lists a data center at Phoenix, Arizona among the sites it operates.",
      "state": "AZ",
      "city": "Goodyear",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Vantage Data Centers",
      "capacity_mw": 160,
      "latitude": 33.40649,
      "longitude": -112.37179,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS ID 110071864472, AZPDES Permit AZC113954) and Vantage Data Centers Phoenix (Goodyear AZ1) campus specification at 14537 W Broadway Rd, Goodyear, Maricopa County, Arizona.",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "EPA ECHO FRS ID 110071864472",
      "location_last_verified": "2026-09-14",
      "site_address": "14537 W Broadway Rd, Goodyear, AZ 85338",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071864472",
      "published": "2026-09-14",
      "last_verified": "2026-10-26",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 3,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://vantage-dc.com/data-center-locations/north-america/phoenix-arizona/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/vantage-phoenix-az",
      "sources": [
        {
          "title": "Vantage breaks ground on Goodyear expansion in Arizona - Data Center Dynamics",
          "url": "https://www.datacenterdynamics.com/en/news/vantage-breaks-ground-on-goodyear-expansion-in-arizona/",
          "publisher": "Data Center Dynamics",
          "date": "2022-10-19",
          "source_tier": 1
        },
        {
          "title": "Vantage Data Centers: Data center locations",
          "url": "https://vantage-dc.com/data-center-locations/",
          "publisher": "Vantage Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "Vantage Data Centers Phase Two in Goodyear | City News | City of Goodyear - goodyearaz.gov",
          "url": "https://www.goodyearaz.gov/Home/Components/News/News/12503/",
          "publisher": "goodyearaz.gov",
          "date": "2022-10-18",
          "source_tier": 1
        },
        {
          "title": "Vantage Data Centers: Vantage Phoenix",
          "url": "https://vantage-dc.com/data-center-locations/north-america/phoenix-arizona/",
          "publisher": "Vantage Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "EPA ECHO detailed facility report: Vantage Data Centers Goodyear AZ1 (110071864472)",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110071864472",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Vantage Data Centers lists Vantage Phoenix at Phoenix, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://vantage-dc.com/data-center-locations/north-america/phoenix-arizona/",
          "source_tier": 2
        },
        {
          "status": "under_construction",
          "effective_at": "2022-10-19",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Vantage Data Centers began the second phase of expansion on its 50 acre Goodyear campus, with 160 MW of IT capacity planned across three facilities totaling over one million square feet, with the second phase scheduled operational in spring 2024.",
          "source_url": "https://www.datacenterdynamics.com/en/news/vantage-breaks-ground-on-goodyear-expansion-in-arizona/",
          "source_tier": 1
        }
      ]
    },
    {
      "slug": "aligned-data-centers-chandler-az",
      "name": "Aligned Data Centers Chandler",
      "summary": "Aligned Data Centers lists 2 data centers at Chandler, Arizona among the sites it operates.",
      "state": "AZ",
      "city": "Chandler",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Aligned Data Centers",
      "capacity_mw": null,
      "latitude": 33.26981,
      "longitude": -111.88791,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS ID 110071276282, MCAQD Air Permit AZMCA000000P000836) and Aligned Data Centers Chandler campus page at 2450 S Price Rd, Chandler, Maricopa County, Arizona.",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "EPA ECHO FRS ID 110071276282",
      "location_last_verified": "2026-09-14",
      "site_address": "2450 S Price Rd, Chandler, AZ 85286",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071276282",
      "published": "2026-09-14",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 2,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://aligneddc.com/phoenix-data-centers/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/aligned-data-centers-chandler-az",
      "sources": [
        {
          "title": "Aligned Data Centers: Data center locations",
          "url": "https://aligneddc.com/locations/",
          "publisher": "Aligned Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "Aligned Data Centers: Aligned PHX-04",
          "url": "https://aligneddc.com/phoenix-data-centers/",
          "publisher": "Aligned Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "EPA ECHO detailed facility report: Aligned PHX06",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110071276282",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Aligned Data Centers lists Aligned PHX-04, Aligned PHX-06 at Chandler, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://aligneddc.com/phoenix-data-centers/",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "aligned-data-centers-phoenix-az",
      "name": "Aligned Data Centers Phoenix",
      "summary": "Aligned Data Centers lists 2 data centers at Phoenix, Arizona among the sites it operates.",
      "state": "AZ",
      "city": "Phoenix",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Aligned Data Centers",
      "capacity_mw": null,
      "latitude": 33.654724,
      "longitude": -112.110141,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS IDs 110070507480 and 110070507328, MCAQD Air Permit AZMCA000000F041775) and Aligned Data Centers Phoenix Union Hills campus page.",
      "location_verified_at": "2026-10-04",
      "coordinate_source": "EPA ECHO FRS ID 110070507480",
      "location_last_verified": "2026-10-04",
      "site_address": "2500 W Union Hills Drive, Phoenix, AZ 85027",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110070507480",
      "published": "2026-09-14",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 4,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://aligneddc.com/phoenix-data-centers/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/aligned-data-centers-phoenix-az",
      "sources": [
        {
          "title": "Aligned Data Centers: Data center locations",
          "url": "https://aligneddc.com/locations/",
          "publisher": "Aligned Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "Aligned Data Centers: Aligned PHX-01/02/03",
          "url": "https://aligneddc.com/phoenix-data-centers/",
          "publisher": "Aligned Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "Aligned Data Centers, APS partner on new Phoenix data center - The Business Journals",
          "url": "https://www.bizjournals.com/phoenix/blog/techflash/2016/03/aligned-data-centers-aps-partner-on-new-phoenix.html",
          "publisher": "The Business Journals",
          "date": "2016-03-28",
          "source_tier": 4
        },
        {
          "title": "EPA ECHO detailed facility report: Aps, Aligned Energy Data Center",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110070507480",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Aligned Data Centers lists Aligned PHX-01/02/03, Aligned PHX-05 at Phoenix, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://aligneddc.com/phoenix-data-centers/",
          "source_tier": 2
        },
        {
          "status": "operational",
          "effective_at": "2016-03-28",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2016-03-28",
          "summary": "Aligned Data Centers partners with APS on new Phoenix data center",
          "source_url": "https://www.bizjournals.com/phoenix/blog/techflash/2016/03/aligned-data-centers-aps-partner-on-new-phoenix.html",
          "source_tier": 4
        }
      ]
    },
    {
      "slug": "aligned-phx-07-waddell-az",
      "name": "Aligned PHX-07",
      "summary": "Aligned Data Centers operates its PHX-07 campus at 14522 W Olive Ave in Waddell, Maricopa County, Arizona (EPA FRS ID 110072218617).",
      "state": "AZ",
      "city": "Waddell",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Aligned Data Centers",
      "capacity_mw": null,
      "latitude": 33.565868,
      "longitude": -112.372701,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS ID 110072218617, Project Eagle Data Center) and Aligned Data Centers Phoenix (PHX-07) campus page at 14522 W Olive Ave, Waddell, Maricopa County, Arizona.",
      "location_verified_at": null,
      "coordinate_source": "EPA ECHO FRS ID 110072218617",
      "location_last_verified": null,
      "site_address": "14522 W Olive Ave, Waddell, AZ 85355",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110072218617",
      "published": "2026-10-21",
      "last_verified": "2026-10-25",
      "cooling_type": "closed_loop_liquid",
      "cooling_type_source_url": "https://aligneddc.com/locations/",
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 2,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://aligneddc.com/phoenix-data-centers/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/aligned-phx-07-waddell-az",
      "sources": [
        {
          "title": "Aligned Data Centers: Data center locations",
          "url": "https://aligneddc.com/locations/",
          "publisher": "Aligned Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "Aligned Data Centers: Aligned PHX-07",
          "url": "https://aligneddc.com/phoenix-data-centers/",
          "publisher": "Aligned Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "EPA ECHO detailed facility report: Project Eagle Data Center / Aligned PHX-07 (110072218617)",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110072218617",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Aligned Data Centers lists Aligned PHX-07 at Waddell, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://aligneddc.com/phoenix-data-centers/",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "apple-mesa-data-center-az",
      "name": "Apple Mesa data center",
      "summary": "Apple operates its global command and data center campus at 3740 S Signal Butte Rd in Mesa, Maricopa County, Arizona (EPA FRS IDs 110072222421 and 110062853416).",
      "state": "AZ",
      "city": "Mesa",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Apple",
      "capacity_mw": null,
      "latitude": 33.34684,
      "longitude": -111.60093,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS IDs 110072222421 and 110062853416, MCAQD Air Permit AZMCA000000F041148) at 3740 S Signal Butte Rd, Mesa, Maricopa County, Arizona.",
      "location_verified_at": null,
      "coordinate_source": "EPA ECHO FRS ID 110072222421",
      "location_last_verified": null,
      "site_address": "3740 S Signal Butte Rd, Mesa, AZ 85212",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110072222421",
      "published": "2026-10-21",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 1,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110072222421",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/apple-mesa-data-center-az",
      "sources": [
        {
          "title": "Apple Environmental Progress Report 2026 (Covering fiscal year 2025, Pages 52–54 & 81)",
          "url": "https://www.apple.com/environment/pdf/Apple_Environmental_Progress_Report_2026.pdf",
          "publisher": "Apple Environmental Progress Report 2026",
          "date": "2026-04-01",
          "source_tier": 2
        },
        {
          "title": "EPA ECHO detailed facility report: Apple Data Center Mesa (110072222421)",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110072222421",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-10-25",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Verified facility status from primary EPA ECHO or operator record.",
          "source_url": "https://echo.epa.gov/detailed-facility-report?fid=110072222421",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "centersquare-phoenix-data-center-az",
      "name": "Centersquare Phoenix data center",
      "summary": "Centersquare lists a data center at Phoenix, Arizona among the sites it operates.",
      "state": "AZ",
      "city": "Mesa",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Centersquare",
      "capacity_mw": null,
      "latitude": 33.421225,
      "longitude": -111.858984,
      "location_precision": "address",
      "location_source": "Centersquare Phoenix (PHX1) facility specification page at 1301 W University Dr, Mesa, Maricopa County, Arizona.",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "operator address point",
      "location_last_verified": "2026-09-14",
      "site_address": "1301 W University Dr, Mesa, AZ 85201",
      "site_address_source_url": "https://www.centersquaredc.com/locations/phoenix",
      "published": "2026-09-14",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 1,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.centersquaredc.com/locations/phoenix",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/centersquare-phoenix-data-center-az",
      "sources": [
        {
          "title": "Centersquare: Data center markets",
          "url": "https://www.csquare.com/data-centers",
          "publisher": "Centersquare",
          "date": "2026-09-14",
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Centersquare lists Centersquare Phoenix data center at Phoenix, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://www.csquare.com/data-centers",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "compass-el-mirage-campus-az",
      "name": "Compass El Mirage campus",
      "summary": "Compass Datacenters lists a data center at El Mirage, Arizona among the sites it operates.",
      "state": "AZ",
      "city": "El Mirage",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Compass Datacenters",
      "capacity_mw": null,
      "latitude": 33.585408,
      "longitude": -112.326811,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS ID 110072129398, Compass Datacenters PHX II) at Peoria Ave and El Mirage Rd, El Mirage, Maricopa County, Arizona.",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "EPA ECHO FRS ID 110072129398",
      "location_last_verified": "2026-09-14",
      "site_address": "12700 W Peoria Ave, El Mirage, AZ 85335",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110072129398",
      "published": "2026-09-14",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 2,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.compassdatacenters.com/locations/phoenix-el-mirage-data-centers/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/compass-el-mirage-campus-az",
      "sources": [
        {
          "title": "Compass Datacenters: Data center markets",
          "url": "https://www.compassdatacenters.com/data-center-markets/",
          "publisher": "Compass Datacenters",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "EPA ECHO detailed facility report: Compass Datacenters PHX II El Mirage (110072129398)",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110072129398",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Compass Datacenters lists Compass El Mirage campus at El Mirage, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://www.compassdatacenters.com/data-center-markets/",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "compass-goodyear-campus-az",
      "name": "Compass Goodyear campus",
      "summary": "Compass Datacenters lists a data center at Goodyear, Arizona among the sites it operates.",
      "state": "AZ",
      "city": "Goodyear",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Compass Datacenters",
      "capacity_mw": null,
      "latitude": 33.442589,
      "longitude": -112.375449,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS IDs 110070550338 and 110071275145, Compass Datacenters PHX I) at 400 S Bullard Ave, Goodyear, Maricopa County, Arizona.",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "EPA ECHO FRS ID 110070550338",
      "location_last_verified": "2026-09-14",
      "site_address": "400 S Bullard Ave, Goodyear, AZ 85338",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110070550338",
      "published": "2026-09-14",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 4,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.compassdatacenters.com/locations/phoenix-goodyear-data-centers/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/compass-goodyear-campus-az",
      "sources": [
        {
          "title": "Compass Datacenters: Data center markets",
          "url": "https://www.compassdatacenters.com/data-center-markets/",
          "publisher": "Compass Datacenters",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "EPA ECHO detailed facility report: Compass Datacenters PHX I Goodyear (110070550338)",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110070550338",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Compass Datacenters lists Compass Goodyear campus at Goodyear, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://www.compassdatacenters.com/data-center-markets/",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "cyrusone-chandler-phx1-phx8-az",
      "name": "CyrusOne Chandler PHX1-PHX8",
      "summary": "CyrusOne operates its Chandler data center campus (PHX1 through PHX8) at 2335 S Ellis St in Chandler, Maricopa County, Arizona (EPA FRS ID 110066858323).",
      "state": "AZ",
      "city": "Chandler",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "CyrusOne",
      "capacity_mw": null,
      "latitude": 33.274675,
      "longitude": -111.884833,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS ID 110066858323, MCAQD Permit AZMCA000000F041145) and CyrusOne Chandler campus page at 2335 S Ellis St, Chandler, Maricopa County, Arizona.",
      "location_verified_at": "2026-10-04",
      "coordinate_source": "EPA ECHO FRS ID 110066858323",
      "location_last_verified": "2026-10-04",
      "site_address": "2335 S Ellis St, Chandler, AZ 85286",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110066858323",
      "published": "2026-09-14",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 7,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.cyrusone.com/data-centers/north-america/chandler-arizona",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/cyrusone-chandler-phx1-phx8-az",
      "sources": [
        {
          "title": "CyrusOne: CyrusOne Chandler PHX1-PHX8",
          "url": "https://www.cyrusone.com/data-centers/north-america/chandler-arizona",
          "publisher": "CyrusOne",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "CyrusOne: Data centers",
          "url": "https://www.cyrusone.com/data-centers",
          "publisher": "CyrusOne",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "EPA ECHO detailed facility report: Cyrusone, Chandler",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110066858323",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "CyrusOne lists CyrusOne Chandler PHX1-PHX8 at Chandler, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://www.cyrusone.com/data-centers/north-america/chandler-arizona",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "databank-ltd-databank-phoenix-phx1-phoenix-az",
      "name": "DataBank Phoenix - PHX1",
      "summary": "DataBank operates its PHX1 downtown Phoenix colocation data center at 3110 N Central Ave in Phoenix, Maricopa County, Arizona.",
      "state": "AZ",
      "city": "Phoenix",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "DataBank",
      "capacity_mw": null,
      "latitude": 33.483936,
      "longitude": -112.0767,
      "location_precision": "address",
      "location_source": "DataBank Phoenix PHX1 facility specification page at 3110 N Central Ave, Phoenix, Maricopa County, Arizona.",
      "location_verified_at": null,
      "coordinate_source": "operator address point",
      "location_last_verified": null,
      "site_address": "3110 N Central Ave, Phoenix, AZ 85012",
      "site_address_source_url": "https://www.databank.com/data-centers/phoenix/downtown-phoenix-data-center-phx1/",
      "published": "2026-10-21",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 1,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.databank.com/data-centers/phoenix/downtown-phoenix-data-center-phx1/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/databank-ltd-databank-phoenix-phx1-phoenix-az",
      "sources": [
        {
          "title": "DataBank: Downtown Phoenix Data Center (PHX1, 3110 N Central Ave)",
          "url": "https://www.databank.com/data-centers/phoenix/downtown-phoenix-data-center-phx1/",
          "publisher": "DataBank",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-10-25",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Verified facility status from primary EPA ECHO or operator record.",
          "source_url": "https://www.databank.com/data-centers/phoenix/downtown-phoenix-data-center-phx1/",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "digital-realty-phoenix-az",
      "name": "Digital Realty Phoenix",
      "summary": "Digital Realty lists 2 data centers at Phoenix, Arizona among the sites it operates.",
      "state": "AZ",
      "city": "Phoenix",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Digital Realty",
      "capacity_mw": null,
      "latitude": 33.451462,
      "longitude": -112.072243,
      "location_precision": "address",
      "location_source": "https://www.digitalrealty.com/data-centers/americas/phoenix",
      "location_verified_at": "2026-10-04",
      "coordinate_source": "https://www.digitalrealty.com/data-centers/americas/phoenix",
      "location_last_verified": "2026-10-04",
      "site_address": "120 East Van Buren Street, Phoenix, AZ 85004",
      "site_address_source_url": "https://www.digitalrealty.com/data-centers/americas/phoenix",
      "published": "2026-09-14",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 1,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.digitalrealty.com/data-centers/phoenix",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/digital-realty-phoenix-az",
      "sources": [
        {
          "title": "Digital Realty: Americas data centers",
          "url": "https://www.digitalrealty.com/data-centers/americas",
          "publisher": "Digital Realty",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "Digital Realty: Digital Realty PHX10",
          "url": "https://www.digitalrealty.com/data-centers/americas/phoenix/phx10",
          "publisher": "Digital Realty",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "Digital Realty: Digital Realty Phoenix",
          "url": "https://www.digitalrealty.com/data-centers/americas/phoenix",
          "publisher": "Digital Realty",
          "date": "2026-09-14",
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Digital Realty lists Digital Realty PHX10, Digital Realty Phoenix at Phoenix, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://www.digitalrealty.com/data-centers/americas/phoenix/phx10",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "digital-realty-phx15-chandler-az",
      "name": "Digital Realty PHX15",
      "summary": "Digital Realty lists a data center at Chandler, Arizona among the sites it operates.",
      "state": "AZ",
      "city": "Chandler",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Digital Realty",
      "capacity_mw": null,
      "latitude": 33.27428,
      "longitude": -111.88906,
      "location_precision": "permit_point",
      "location_source": "https://echo.epa.gov/detailed-facility-report?fid=110055586236",
      "location_verified_at": "2026-10-04",
      "coordinate_source": "https://echo.epa.gov/detailed-facility-report?fid=110055586236",
      "location_last_verified": "2026-10-04",
      "site_address": "2121 S Price RD, Chandler, AZ 85248",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110055586236",
      "published": "2026-09-14",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 1,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.digitalrealty.com/data-centers/phoenix",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/digital-realty-phx15-chandler-az",
      "sources": [
        {
          "title": "Digital Realty: Americas data centers",
          "url": "https://www.digitalrealty.com/data-centers/americas",
          "publisher": "Digital Realty",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "Digital Realty: Digital Realty PHX15",
          "url": "https://www.digitalrealty.com/data-centers/americas/phoenix/phx15",
          "publisher": "Digital Realty",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "EPA ECHO detailed facility report: Digital Realty Trust Chandler, LLC",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110055586236",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Digital Realty lists Digital Realty PHX15 at Chandler, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://www.digitalrealty.com/data-centers/americas/phoenix/phx15",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "edgeconnex-inc-edgeconnex-phoenix-edcphx01-tempe-az",
      "name": "EdgeConneX Phoenix (EDCPHX01)",
      "summary": "EdgeConneX operates its PHX01 edge colocation data center at 3011 S 52nd St in Tempe, Maricopa County, Arizona.",
      "state": "AZ",
      "city": "Tempe",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "EdgeConneX",
      "capacity_mw": null,
      "latitude": 33.395544,
      "longitude": -111.97012,
      "location_precision": "address",
      "location_source": "EdgeConneX Phoenix (PHX01) facility specification page at 3011 S 52nd St, Tempe, Maricopa County, Arizona.",
      "location_verified_at": null,
      "coordinate_source": "operator address point",
      "location_last_verified": null,
      "site_address": "3011 S 52nd St, Tempe, AZ 85282",
      "site_address_source_url": "https://www.edgeconnex.com/locations/americas/phoenix-az/",
      "published": "2026-10-21",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 1,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.edgeconnex.com/locations/americas/phoenix-az/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/edgeconnex-inc-edgeconnex-phoenix-edcphx01-tempe-az",
      "sources": [
        {
          "title": "EdgeConneX: Phoenix (Tempe and Mesa) Data Center Specifications",
          "url": "https://www.edgeconnex.com/locations/americas/phoenix-az/",
          "publisher": "EdgeConneX",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-10-25",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Verified facility status from primary EPA ECHO or operator record.",
          "source_url": "https://www.edgeconnex.com/locations/americas/phoenix-az/",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "edgeconnex-mesa-data-center-campus-az",
      "name": "EdgeConneX Mesa data center campus",
      "summary": "EdgeConneX operates its two building Mesa hyperscale data center campus (PHX02 and PHX03) at 3261 S Hawes Rd in Mesa, Maricopa County, Arizona (EPA FRS IDs 110071988389 and 110071815477).",
      "state": "AZ",
      "city": "Mesa",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "EdgeConneX",
      "capacity_mw": null,
      "latitude": 33.358008,
      "longitude": -111.653231,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS IDs 110071988389 and 110071815477, AZPDES Permit AZC113987) and EdgeConneX Phoenix Mesa campus specification at 3261 S Hawes Rd, Mesa, Maricopa County, Arizona.",
      "location_verified_at": "2026-10-06",
      "coordinate_source": "EPA ECHO FRS ID 110071988389",
      "location_last_verified": "2026-10-06",
      "site_address": "3261 S Hawes Rd, Mesa, AZ 85212",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071988389",
      "published": "2026-09-27",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 2,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.edgeconnex.com/locations/americas/phoenix-az/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/edgeconnex-mesa-data-center-campus-az",
      "sources": [
        {
          "title": "EdgeConneX proposes multi-phase data center campus in Mesa - The Business Journals",
          "url": "https://www.bizjournals.com/phoenix/news/2023/09/01/edgeconnex-new-data-center-campus-mesa.html",
          "publisher": "The Business Journals",
          "date": "2023-09-01",
          "source_tier": 1
        },
        {
          "title": "EPA ECHO detailed facility report: Edgeconnex PHX11",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110071988389",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-10-25",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Verified facility status from primary EPA ECHO or operator record.",
          "source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071988389",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "edgecore-mesa-north-campus-az",
      "name": "EdgeCore Mesa North Campus",
      "summary": "EdgeCore's Mesa North Campus in Mesa, Arizona, resized and approved by the city in March 2026.",
      "state": "AZ",
      "city": "Mesa",
      "county": "Maricopa County",
      "status": "permitting",
      "developer": "EdgeCore",
      "capacity_mw": null,
      "latitude": 33.34754,
      "longitude": -111.62088,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS IDs 110071645018 and 110071513551, AZPDES Permits AZC102385 and AZC113553) and EdgeCore Phoenix Mesa campus page.",
      "location_verified_at": "2026-09-23",
      "coordinate_source": "EPA ECHO FRS ID 110071645018",
      "location_last_verified": "2026-09-23",
      "site_address": "3856 S Everton Ter, Mesa, AZ 85212",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071645018",
      "published": "2026-09-08",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 3,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://edgecore.com/locations/phoenix/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/edgecore-mesa-north-campus-az",
      "sources": [
        {
          "title": "EdgeCore expands Mesa data center campus in Arizona",
          "url": "https://www.datacenterdynamics.com/en/news/edgecore-expands-mesa-data-center-campus-in-arizona/",
          "publisher": "Data Center Dynamics",
          "date": "2025-05-21",
          "source_tier": 3
        },
        {
          "title": "Denver's EdgeCore scales back Mesa data center campus",
          "url": "https://www.bizjournals.com/phoenix/news/2026/03/10/data-center-campus-proposed-in-mesa-downsizes.html",
          "publisher": "The Business Journals",
          "date": "2026-03-10",
          "source_tier": 4
        },
        {
          "title": "EdgeCore Returns With Revised Mesa Data Center Plan",
          "url": "https://realestatedaily-news.com/edgecore-returns-with-revised-mesa-data-center-plan/",
          "publisher": "Real Estate Daily News",
          "date": "2026-03-11",
          "source_tier": 4
        },
        {
          "title": "Re-sized data center in Mesa sails to approval",
          "url": "https://www.themesatribune.com/news/re-sized-data-center-in-mesa-sails-to-approval/article_a0ece120-74c7-476b-a64e-ff4015ee7e27.html",
          "publisher": "themesatribune.com",
          "date": "2026-03-15",
          "source_tier": 4
        },
        {
          "title": "EdgeCore Gains Zoning Approval For Scaled-Back Mesa Data Center",
          "url": "https://www.bisnow.com/news/phoenix/industrial/edgecore-gains-board-approval-after-scaling-back-mesa-data-center-plan-133677",
          "publisher": "Bisnow",
          "date": "2026-03-16",
          "source_tier": 3
        },
        {
          "title": "EdgeCore Digital Infrastructure: Phoenix (Mesa) Campus Specifications",
          "url": "https://edgecore.com/locations/phoenix/",
          "publisher": "EdgeCore Digital Infrastructure",
          "date": null,
          "source_tier": 2
        },
        {
          "title": "EPA ECHO detailed facility report: EdgeCore Data Center North Campus (110071645018)",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110071645018",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "permitting",
          "effective_at": "2026-03-16",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Generator testing restricted to 9 a.m. to 9 p.m. at EdgeCore facility",
          "source_url": "https://www.bisnow.com/news/phoenix/industrial/edgecore-gains-board-approval-after-scaling-back-mesa-data-center-plan-133677",
          "source_tier": 3
        },
        {
          "status": "permitting",
          "effective_at": "2026-03-16",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "EdgeCore scaled back proposed data center from 2.1 million square feet to 1.2 million square feet",
          "source_url": "https://www.bisnow.com/news/phoenix/industrial/edgecore-gains-board-approval-after-scaling-back-mesa-data-center-plan-133677",
          "source_tier": 3
        },
        {
          "status": "permitting",
          "effective_at": "2026-03-15",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "EdgeCore will build a 1.2 million square foot data center in southeast Mesa, cut from the original 2.1 million square foot plan",
          "source_url": "https://www.themesatribune.com/news/re-sized-data-center-in-mesa-sails-to-approval/article_a0ece120-74c7-476b-a64e-ff4015ee7e27.html",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-03-11",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "EdgeCore exploring 750 acre site in Florence for future data center campus as part of 1,500 acre industrial technology park",
          "source_url": "https://realestatedaily-news.com/edgecore-returns-with-revised-mesa-data-center-plan/",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-03-11",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Full buildout includes original 180,000 square foot data center and two additional buildings PH02 and PH03 under construction",
          "source_url": "https://realestatedaily-news.com/edgecore-returns-with-revised-mesa-data-center-plan/",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-03-11",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "EdgeCore acquired 43.87 acres in Mesa for $43.95 million in May 2025",
          "source_url": "https://realestatedaily-news.com/edgecore-returns-with-revised-mesa-data-center-plan/",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-03-11",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Original plan featured three separate buildings and 350,000 square foot SRP substation with 250 megawatts capacity",
          "source_url": "https://realestatedaily-news.com/edgecore-returns-with-revised-mesa-data-center-plan/",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-03-11",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "EdgeCore revised plan reduces expansion to two buildings totaling 1,236,960 square feet",
          "source_url": "https://realestatedaily-news.com/edgecore-returns-with-revised-mesa-data-center-plan/",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-03-11",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "EdgeCore originally secured approval in January 2024 for 2.1 million square foot expansion",
          "source_url": "https://realestatedaily-news.com/edgecore-returns-with-revised-mesa-data-center-plan/",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-03-10",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "EdgeCore data center campus in Mesa being scaled back",
          "source_url": "https://www.bizjournals.com/phoenix/news/2026/03/10/data-center-campus-proposed-in-mesa-downsizes.html",
          "source_tier": 4
        },
        {
          "status": "rumored",
          "effective_at": "2025-05-21",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "EdgeCore expands Mesa data center campus in May 2025",
          "source_url": "https://www.datacenterdynamics.com/en/news/edgecore-expands-mesa-data-center-campus-in-arizona/",
          "source_tier": 3
        }
      ]
    },
    {
      "slug": "flexential-corp-flexential-phoenix-phx01-phoenix-az",
      "name": "Flexential Phoenix - PHX01",
      "summary": "Flexential operates its PHX01 colocation data center at 1850 W Deer Valley Rd in Phoenix, Maricopa County, Arizona.",
      "state": "AZ",
      "city": "Phoenix",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Flexential",
      "capacity_mw": null,
      "latitude": 33.684671,
      "longitude": -112.098312,
      "location_precision": "address",
      "location_source": "Flexential Phoenix (PHX01) facility specification page at 1850 W Deer Valley Rd, Phoenix, Maricopa County, Arizona.",
      "location_verified_at": null,
      "coordinate_source": "operator address point",
      "location_last_verified": null,
      "site_address": "1850 W Deer Valley Rd, Phoenix, AZ 85027",
      "site_address_source_url": "https://www.flexential.com/data-centers/arizona/phoenix",
      "published": "2026-10-21",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 1,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.flexential.com/data-centers/arizona/phoenix",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/flexential-corp-flexential-phoenix-phx01-phoenix-az",
      "sources": [
        {
          "title": "Flexential: Phoenix Data Center (1850 W Deer Valley Rd)",
          "url": "https://www.flexential.com/data-centers/arizona/phoenix",
          "publisher": "Flexential",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-10-25",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Verified facility status from primary EPA ECHO or operator record.",
          "source_url": "https://www.flexential.com/data-centers/arizona/phoenix",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "google-mesa-data-center-az",
      "name": "Google Mesa data center",
      "summary": "Google described a recently announced data center in Mesa, Arizona in a December 2023 blog post and said it chose air cooling after finding the local water source at high risk of scarcity and depletion.",
      "state": "AZ",
      "city": "Mesa",
      "county": "Maricopa County",
      "status": "under_construction",
      "developer": "Google",
      "capacity_mw": null,
      "latitude": 33.349,
      "longitude": -111.668,
      "location_precision": "address",
      "location_source": "Google Mesa data center campus at E Elliot Rd and S Sossaman Rd (7535 E Ray Rd), Mesa, Maricopa County, Arizona.",
      "location_verified_at": "2026-09-23",
      "coordinate_source": "operator address point",
      "location_last_verified": "2026-09-23",
      "site_address": "7535 E Ray Rd, Mesa, AZ 85212",
      "site_address_source_url": "https://cloud.google.com/blog/topics/sustainability/assessing-watershed-health-in-data-center-host-communities",
      "published": "2026-09-07",
      "last_verified": "2026-10-25",
      "cooling_type": "air",
      "cooling_type_source_url": "https://cloud.google.com/blog/topics/sustainability/assessing-watershed-health-in-data-center-host-communities",
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 2,
      "buildings_basis": "site plan",
      "buildings_source_url": "https://cloud.google.com/blog/topics/sustainability/assessing-watershed-health-in-data-center-host-communities",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/google-mesa-data-center-az",
      "sources": [
        {
          "title": "Assessing watershed health in data center host communities",
          "url": "https://cloud.google.com/blog/topics/sustainability/assessing-watershed-health-in-data-center-host-communities",
          "publisher": "Google Cloud Blog",
          "date": "2023-12-14",
          "source_tier": 2
        },
        {
          "title": "Google details plans on its huge data center underway in Mesa",
          "url": "https://www.bizjournals.com/phoenix/news/2023/09/06/google-mesa-data-center-campus.html",
          "publisher": "The Business Journals",
          "date": "2023-09-06",
          "source_tier": 4
        },
        {
          "title": "In lieu of water cooling, Google locks down renewables for Mesa data center",
          "url": "https://www.latitudemedia.com/news/in-lieu-of-water-cooling-google-locks-down-renewables-for-mesa-data-center/",
          "publisher": "Latitude Media",
          "date": "2024-03-14",
          "source_tier": 4
        },
        {
          "title": "Our work to build a more sustainable future in Arizona",
          "url": "https://blog.google/company-news/outreach-and-initiatives/sustainability/google-carbon-free-data-center-arizona-/",
          "publisher": "blog.google",
          "date": "2024-03-14",
          "source_tier": 4
        },
        {
          "title": "Google reaches clean energy agreement with SRP for Mesa data center",
          "url": "https://www.azcentral.com/story/money/business/2024/03/14/google-reaches-clean-energy-agreement-with-srp-for-mesa-data-center/72970682007/",
          "publisher": "azcentral.com and The Arizona Republic",
          "date": "2024-03-14",
          "source_tier": 4
        },
        {
          "title": "Google: Data center locations",
          "url": "https://datacenters.google/locations/",
          "publisher": "Google",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "Mesa lands Google data center. Here's a look at the deal",
          "url": "https://www.azcentral.com/story/news/local/mesa/2019/06/28/mesa-offers-tax-break-land-google-data-center-elliott-road-technology-corridor/1590854001/",
          "publisher": "azcentral.com and The Arizona Republic",
          "date": "2019-06-28",
          "source_tier": 4
        },
        {
          "title": "Is Google coming to Mesa? $1B data center proposed",
          "url": "https://www.youtube.com/watch?v=pld4TofrWP8",
          "publisher": "YouTube",
          "date": "2019-07-01",
          "source_tier": 5
        },
        {
          "title": "Mesa lands big Google data center",
          "url": "https://www.eastvalleytribune.com/news/mesa-lands-big-google-data-center/article_9b683728-99f9-11e9-9943-6bad7244231f.html",
          "publisher": "East Valley Tribune",
          "date": "2019-07-01",
          "source_tier": 4
        },
        {
          "title": "Amazon, Google expand E. Mesa footprint",
          "url": "https://www.gilbertsunnews.com/news/amazon-google-expand-e-mesa-footprint/article_c8c25dd4-151a-11ee-9403-bf55cb84405a.html",
          "publisher": "gilbertsunnews.com",
          "date": "2023-07-01",
          "source_tier": 4
        },
        {
          "title": "Google breaks ground on Mesa data center campus in Arizona",
          "url": "https://www.datacenterdynamics.com/en/news/google-breaks-ground-on-mesa-data-center-campus-in-arizona/",
          "publisher": "Data Center Dynamics",
          "date": "2023-07-12",
          "source_tier": 3
        },
        {
          "title": "Google announces $600 million data center coming to Mesa",
          "url": "https://www.azfamily.com/2023/09/06/google-announces-600-million-data-center-coming-mesa/",
          "publisher": "AZ Family",
          "date": "2023-09-06",
          "source_tier": 4
        },
        {
          "title": "Google building a $600 million data center in Mesa that won't use water to cool storage units",
          "url": "https://www.12news.com/article/news/local/valley/google-is-building-a-600-million-data-center-in-mesa-that-wont-use-water-to-cool-storage-units/75-423d5f59-5c3e-4160-b587-0a328eec9a83",
          "publisher": "12News",
          "date": "2023-09-06",
          "source_tier": 4
        },
        {
          "title": "Arizona's 1st Google facility will be $600M data center in Mesa",
          "url": "https://www.azcentral.com/picture-gallery/news/local/mesa/2023/09/06/arizonas-1st-google-facility-will-be-600m-data-center-in-mesa/70778940007/",
          "publisher": "azcentral.com and The Arizona Republic",
          "date": "2023-09-06",
          "source_tier": 4
        },
        {
          "title": "Google to build $600 million data center in Mesa",
          "url": "https://kjzz.org/content/1856930/google-breaks-ground-600-million-mesa-data-center",
          "publisher": "KJZZ",
          "date": "2023-09-07",
          "source_tier": 4
        },
        {
          "title": "Google coming to Valley for first time with $600 million data center in Mesa",
          "url": "https://www.abc15.com/news/region-southeast-valley/mesa/google-coming-to-valley-for-first-time-with-600-million-data-center-in-mesa",
          "publisher": "abc15.com",
          "date": "2023-09-07",
          "source_tier": 4
        },
        {
          "title": "Land and Expand: Google, Vantage Data Centers, Microsoft",
          "url": "https://www.datacenterfrontier.com/site-selection/article/33011236/land-and-expand-google-vantage-data-centers-microsoft",
          "publisher": "Data Center Frontier",
          "date": "2023-09-08",
          "source_tier": 3
        },
        {
          "title": "Google Breaks Ground On $600M Data Center In Mesa, AZ",
          "url": "https://businessfacilities.com/google-breaks-ground-on-600m-data-center-in-mesa-az/",
          "publisher": "Business Facilities",
          "date": "2023-09-08",
          "source_tier": 4
        },
        {
          "title": "Google breaks ground on massive $600 million Mesa data center",
          "url": "https://azbigmedia.com/business/google-breaks-ground-on-massive-600-million-mesa-data-center/",
          "publisher": "AZ Big Media",
          "date": "2023-09-09",
          "source_tier": 4
        },
        {
          "title": "Google data center's next phase goes to Mesa for review",
          "url": "https://www.abc15.com/news/business/google-data-centers-next-phase-goes-to-mesa-for-review",
          "publisher": "abc15.com",
          "date": "2024-04-09",
          "source_tier": 4
        },
        {
          "title": "Google data center's next phase goes to Mesa for review",
          "url": "https://www.bizjournals.com/phoenix/news/2024/04/09/google-redhawk-second-phase-mesa-design-review.html",
          "publisher": "The Business Journals",
          "date": "2024-04-09",
          "source_tier": 4
        },
        {
          "title": "Google files to build second data center at Mesa campus in Arizona",
          "url": "https://www.datacenterdynamics.com/en/news/google-files-to-build-second-data-center-at-mesa-campus-in-arizona/",
          "publisher": "Data Center Dynamics",
          "date": "2024-04-10",
          "source_tier": 3
        },
        {
          "title": "SRP and Google Launch Collaboration to Advance Long Duration Energy Storage Innovation, Grid Resilience in Arizona",
          "url": "https://media.srpnet.com/srp-and-google-launch-collaboration-to-advance-long-duration-energy-storage-innovation-grid-resilience-in-arizona/",
          "publisher": "SRP Newsroom",
          "date": "2025-09-08",
          "source_tier": 4
        },
        {
          "title": "Large data centers are popping up all over Mesa. See photos",
          "url": "https://www.azcentral.com/picture-gallery/news/local/mesa/2026/02/02/data-centers-mesa-meta-google-photos/88160325007/",
          "publisher": "azcentral.com and The Arizona Republic",
          "date": "2026-02-02",
          "source_tier": 4
        },
        {
          "title": "Google is building a $1B data center campus in Mesa, Arizona",
          "url": "https://constructionreviewonline.com/google-is-building-a-1b-data-center-campus-in-mesa-arizona/",
          "publisher": "Construction Review",
          "date": "2026-05-07",
          "source_tier": 4
        },
        {
          "title": "Google announces donation for Arizona water restoration project",
          "url": "https://www.abc15.com/weather/impact-earth/google-announces-donation-for-arizona-water-restoration-project",
          "publisher": "ABC15 Arizona",
          "date": "2026-08-25",
          "source_tier": 4
        },
        {
          "title": "Mesa Council approves $1bn Google data center, with $16m in tax breaks",
          "url": "https://www.datacenterdynamics.com/en/news/mesa-council-approves-1bn-google-arizona-data-center-16m-tax-breaks/",
          "publisher": "Data Center Dynamics",
          "date": "2019-07-03",
          "source_tier": 3
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "under_construction",
          "effective_at": "2026-08-25",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google Mesa data center began functioning within the past year",
          "source_url": "https://www.abc15.com/weather/impact-earth/google-announces-donation-for-arizona-water-restoration-project",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-05-07",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google entered GPLET agreement with Mesa for 25 year term with reduced property taxes",
          "source_url": "https://constructionreviewonline.com/google-is-building-a-1b-data-center-campus-in-mesa-arizona/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-05-07",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Project Red Hawk site is approximately 185 acres at northwest corner of Sossaman and Elliot roads",
          "source_url": "https://constructionreviewonline.com/google-is-building-a-1b-data-center-campus-in-mesa-arizona/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-05-07",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Entire project expected to be completed by 2030",
          "source_url": "https://constructionreviewonline.com/google-is-building-a-1b-data-center-campus-in-mesa-arizona/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-05-07",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "By 2029 minimum investment is $1 billion with 750,000 square feet of development",
          "source_url": "https://constructionreviewonline.com/google-is-building-a-1b-data-center-campus-in-mesa-arizona/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-05-07",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "By 2027 Google must invest $800 million including taxable construction costs and construct 500,000 square feet",
          "source_url": "https://constructionreviewonline.com/google-is-building-a-1b-data-center-campus-in-mesa-arizona/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-05-07",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Total site plan outlines future stages totaling 750,000 square feet",
          "source_url": "https://constructionreviewonline.com/google-is-building-a-1b-data-center-campus-in-mesa-arizona/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-05-07",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "First phase includes 288,530 square foot data center building, utility switchyard, medium voltage substation, security kiosk, road upgrades, and employee office building",
          "source_url": "https://constructionreviewonline.com/google-is-building-a-1b-data-center-campus-in-mesa-arizona/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-05-07",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "First phase must be completed by July 2025",
          "source_url": "https://constructionreviewonline.com/google-is-building-a-1b-data-center-campus-in-mesa-arizona/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-02-02",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google data center operates in Mesa, Arizona, photographed January 6, 2026",
          "source_url": "https://www.azcentral.com/picture-gallery/news/local/mesa/2026/02/02/data-centers-mesa-meta-google-photos/88160325007/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2025-09-08",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "SRP issued RFPs in 2022 and 2024 for LDES technology demonstration projects.",
          "source_url": "https://media.srpnet.com/srp-and-google-launch-collaboration-to-advance-long-duration-energy-storage-innovation-grid-resilience-in-arizona/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2025-09-08",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google's future data center in Mesa is supported by Sonoran Solar Energy Center (260 MW solar with 1 GWh battery storage), Storey Energy Center (88 MW solar and battery storage), and Babbitt Ranch Energy Center (161 MW wind farm).",
          "source_url": "https://media.srpnet.com/srp-and-google-launch-collaboration-to-advance-long-duration-energy-storage-innovation-grid-resilience-in-arizona/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2024-04-10",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google filed to build second data center at Mesa campus",
          "source_url": "https://www.datacenterdynamics.com/en/news/google-files-to-build-second-data-center-at-mesa-campus-in-arizona/",
          "source_tier": 3
        },
        {
          "status": "under_construction",
          "effective_at": "2024-04-09",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google data center project in Mesa, Arizona advancing to review phase in 2024",
          "source_url": "https://www.bizjournals.com/phoenix/news/2024/04/09/google-redhawk-second-phase-mesa-design-review.html",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2024-04-09",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Second phase of Google Mesa data center is 280,000 square feet",
          "source_url": "https://www.abc15.com/news/business/google-data-centers-next-phase-goes-to-mesa-for-review",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2024-04-09",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google Mesa data center first phase site is more than 185 acres near northwest corner of Sossaman and Elliot roads",
          "source_url": "https://www.abc15.com/news/business/google-data-centers-next-phase-goes-to-mesa-for-review",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2024-03-14",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Data center set to come online in 2025",
          "source_url": "https://www.latitudemedia.com/news/in-lieu-of-water-cooling-google-locks-down-renewables-for-mesa-data-center/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2024-03-14",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google signed eight year contract with Salt River Project for 434 MW of renewable energy",
          "source_url": "https://www.latitudemedia.com/news/in-lieu-of-water-cooling-google-locks-down-renewables-for-mesa-data-center/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2024-03-14",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google reached a clean energy agreement with SRP for the Mesa data center",
          "source_url": "https://www.azcentral.com/story/money/business/2024/03/14/google-reaches-clean-energy-agreement-with-srp-for-mesa-data-center/72970682007/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2024-03-14",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Mesa data center will use air cooled technology and be operational in 2025",
          "source_url": "https://blog.google/company-news/outreach-and-initiatives/sustainability/google-carbon-free-data-center-arizona-/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2024-03-14",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Data center will use air cooling technology instead of water cooling",
          "source_url": "https://www.latitudemedia.com/news/in-lieu-of-water-cooling-google-locks-down-renewables-for-mesa-data-center/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2023-12-14",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google said the water source for its Mesa, Arizona data center was at high risk of scarcity and depletion and that it chose air cooling in response; a company statement about its own planning, not an independent audit",
          "source_url": "https://cloud.google.com/blog/topics/sustainability/assessing-watershed-health-in-data-center-host-communities",
          "source_tier": 2
        },
        {
          "status": "under_construction",
          "effective_at": "2023-09-09",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "This will be Google's first physical presence in Arizona",
          "source_url": "https://azbigmedia.com/business/google-breaks-ground-on-massive-600-million-mesa-data-center/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2023-09-09",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google broke ground on a new $600 million data center in Mesa",
          "source_url": "https://azbigmedia.com/business/google-breaks-ground-on-massive-600-million-mesa-data-center/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2023-09-09",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google announced a new Google Cloud region is coming to Phoenix",
          "source_url": "https://azbigmedia.com/business/google-breaks-ground-on-massive-600-million-mesa-data-center/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2023-09-09",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "The Mesa data center will use state of the art air cool technology",
          "source_url": "https://azbigmedia.com/business/google-breaks-ground-on-massive-600-million-mesa-data-center/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2023-09-08",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google expects to start building at the site near the beginning of 2024 and be complete by early 2025",
          "source_url": "https://www.datacenterfrontier.com/site-selection/article/33011236/land-and-expand-google-vantage-data-centers-microsoft",
          "source_tier": 3
        },
        {
          "status": "under_construction",
          "effective_at": "2023-09-08",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google breaks ground on data center in Mesa, Arizona in September 2023",
          "source_url": "https://businessfacilities.com/google-breaks-ground-on-600m-data-center-in-mesa-az/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2023-09-08",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google is looking to buy other large parcels of land for future growth in the area",
          "source_url": "https://www.datacenterfrontier.com/site-selection/article/33011236/land-and-expand-google-vantage-data-centers-microsoft",
          "source_tier": 3
        },
        {
          "status": "under_construction",
          "effective_at": "2023-09-08",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google uses air cooled technology and uses no water in its cooling technology",
          "source_url": "https://www.datacenterfrontier.com/site-selection/article/33011236/land-and-expand-google-vantage-data-centers-microsoft",
          "source_tier": 3
        },
        {
          "status": "under_construction",
          "effective_at": "2023-09-08",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google's Mesa data center project is valued at $600 million and was previously known as Project Red Hawk",
          "source_url": "https://www.datacenterfrontier.com/site-selection/article/33011236/land-and-expand-google-vantage-data-centers-microsoft",
          "source_tier": 3
        },
        {
          "status": "under_construction",
          "effective_at": "2023-09-07",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Nearly 190 acres of former farmland converted to computing compound",
          "source_url": "https://kjzz.org/content/1856930/google-breaks-ground-600-million-mesa-data-center",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2023-09-07",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google broke ground on September 6, 2023 on a $600 million data center in Mesa",
          "source_url": "https://kjzz.org/content/1856930/google-breaks-ground-600-million-mesa-data-center",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2023-09-07",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google Cloud region announced for Phoenix",
          "source_url": "https://www.abc15.com/news/region-southeast-valley/mesa/google-coming-to-valley-for-first-time-with-600-million-data-center-in-mesa",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2023-09-07",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google Mesa data center serves Google Search, Gmail, Maps and Google Cloud services",
          "source_url": "https://www.abc15.com/news/region-southeast-valley/mesa/google-coming-to-valley-for-first-time-with-600-million-data-center-in-mesa",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2023-09-07",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "First phase expected to be finished in summer 2025",
          "source_url": "https://kjzz.org/content/1856930/google-breaks-ground-600-million-mesa-data-center",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2023-09-06",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google committed to air cooled technology to limit water usage",
          "source_url": "https://www.azfamily.com/2023/09/06/google-announces-600-million-data-center-coming-mesa/",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2023-09-06",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Data center will be first physical Google presence in Arizona",
          "source_url": "https://www.azfamily.com/2023/09/06/google-announces-600-million-data-center-coming-mesa/",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2023-09-06",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google is building a $600 million data center in Mesa, Arizona",
          "source_url": "https://www.azcentral.com/picture-gallery/news/local/mesa/2023/09/06/arizonas-1st-google-facility-will-be-600m-data-center-in-mesa/70778940007/",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2023-09-06",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google Mesa data center uses air cooling instead of water cooling",
          "source_url": "https://www.12news.com/article/news/local/valley/google-is-building-a-600-million-data-center-in-mesa-that-wont-use-water-to-cool-storage-units/75-423d5f59-5c3e-4160-b587-0a328eec9a83",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2023-09-06",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google detailed plans on huge data center underway in Mesa",
          "source_url": "https://www.bizjournals.com/phoenix/news/2023/09/06/google-mesa-data-center-campus.html",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2023-07-12",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google broke ground on Mesa data center campus",
          "source_url": "https://www.datacenterdynamics.com/en/news/google-breaks-ground-on-mesa-data-center-campus-in-arizona/",
          "source_tier": 3
        },
        {
          "status": "permitting",
          "effective_at": "2023-07-01",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google faces July 2025 deadline for 250,000 square feet of development and $600 million capital investment",
          "source_url": "https://www.gilbertsunnews.com/news/amazon-google-expand-e-mesa-footprint/article_c8c25dd4-151a-11ee-9403-bf55cb84405a.html",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2023-07-01",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google received Design Review Board approval for 288,000 square foot data hall as phase 1",
          "source_url": "https://www.gilbertsunnews.com/news/amazon-google-expand-e-mesa-footprint/article_c8c25dd4-151a-11ee-9403-bf55cb84405a.html",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2023-07-01",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Mesa City Council approved development agreement in 2019",
          "source_url": "https://www.gilbertsunnews.com/news/amazon-google-expand-e-mesa-footprint/article_c8c25dd4-151a-11ee-9403-bf55cb84405a.html",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2023-07-01",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Total planned development on 186 acre site is 750,000 square feet",
          "source_url": "https://www.gilbertsunnews.com/news/amazon-google-expand-e-mesa-footprint/article_c8c25dd4-151a-11ee-9403-bf55cb84405a.html",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2019-07-03",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "City of Mesa provided $16 million in tax breaks for the data center",
          "source_url": "https://www.datacenterdynamics.com/en/news/mesa-council-approves-1bn-google-arizona-data-center-16m-tax-breaks/",
          "source_tier": 3
        },
        {
          "status": "approved",
          "effective_at": "2019-07-03",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Mesa City Council approved $1 billion Google data center",
          "source_url": "https://www.datacenterdynamics.com/en/news/mesa-council-approves-1bn-google-arizona-data-center-16m-tax-breaks/",
          "source_tier": 3
        },
        {
          "status": "approved",
          "effective_at": "2019-07-01",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Property is 186 acres located at Elliot and Sossaman roads in southeast Mesa",
          "source_url": "https://www.eastvalleytribune.com/news/mesa-lands-big-google-data-center/article_9b683728-99f9-11e9-9943-6bad7244231f.html",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2019-07-01",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google has up to five years to begin construction and up to 10 years to finish building",
          "source_url": "https://www.eastvalleytribune.com/news/mesa-lands-big-google-data-center/article_9b683728-99f9-11e9-9943-6bad7244231f.html",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2019-07-01",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Mesa City Council is primed to approve the development agreement at Monday meeting",
          "source_url": "https://www.eastvalleytribune.com/news/mesa-lands-big-google-data-center/article_9b683728-99f9-11e9-9943-6bad7244231f.html",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2019-07-01",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "750,000 square foot requirement by July 2029 with at least $1 billion investment",
          "source_url": "https://www.eastvalleytribune.com/news/mesa-lands-big-google-data-center/article_9b683728-99f9-11e9-9943-6bad7244231f.html",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2019-07-01",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "500,000 square foot requirement by July 2027 with minimum investment of $800 million",
          "source_url": "https://www.eastvalleytribune.com/news/mesa-lands-big-google-data-center/article_9b683728-99f9-11e9-9943-6bad7244231f.html",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2019-07-01",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Construction of at least 250,000 square feet required by July 2025 with $600 million investment",
          "source_url": "https://www.eastvalleytribune.com/news/mesa-lands-big-google-data-center/article_9b683728-99f9-11e9-9943-6bad7244231f.html",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2019-07-01",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google will build a data center in Mesa, Arizona in the Elliot Road Technology Corridor",
          "source_url": "https://www.eastvalleytribune.com/news/mesa-lands-big-google-data-center/article_9b683728-99f9-11e9-9943-6bad7244231f.html",
          "source_tier": 4
        },
        {
          "status": "proposed",
          "effective_at": "2019-07-01",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "If approved, Google has five years to start construction",
          "source_url": "https://www.youtube.com/watch?v=pld4TofrWP8",
          "source_tier": 5
        },
        {
          "status": "proposed",
          "effective_at": "2019-07-01",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "The development agreement includes a $16 million tax break",
          "source_url": "https://www.youtube.com/watch?v=pld4TofrWP8",
          "source_tier": 5
        },
        {
          "status": "proposed",
          "effective_at": "2019-07-01",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google proposed a 750,000 square foot data center at Sossaman and Elliot Roads in Mesa",
          "source_url": "https://www.youtube.com/watch?v=pld4TofrWP8",
          "source_tier": 5
        },
        {
          "status": "approved",
          "effective_at": "2019-06-28",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "The data center property comprises 186 acres of farmland at the northwest corner of Elliot and Sossaman Road",
          "source_url": "https://www.azcentral.com/story/news/local/mesa/2019/06/28/mesa-offers-tax-break-land-google-data-center-elliott-road-technology-corridor/1590854001/",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2019-06-28",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google would spend $1 billion to build 750,000 square feet by July 2029",
          "source_url": "https://www.azcentral.com/story/news/local/mesa/2019/06/28/mesa-offers-tax-break-land-google-data-center-elliott-road-technology-corridor/1590854001/",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2019-06-28",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Google would build 250,000 square feet in the first phase by July 2025",
          "source_url": "https://www.azcentral.com/story/news/local/mesa/2019/06/28/mesa-offers-tax-break-land-google-data-center-elliott-road-technology-corridor/1590854001/",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2019-06-28",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Mesa City Council voted to approve a development agreement for a Google data center at Elliot Road Technology Corridor on June 24, 2019 (vote was scheduled for Monday)",
          "source_url": "https://www.azcentral.com/story/news/local/mesa/2019/06/28/mesa-offers-tax-break-land-google-data-center-elliott-road-technology-corridor/1590854001/",
          "source_tier": 4
        }
      ]
    },
    {
      "slug": "h5-phoenix-az",
      "name": "H5 Phoenix",
      "summary": "H5 Data Centers lists a data center at Phoenix, Arizona among the sites it operates.",
      "state": "AZ",
      "city": "Chandler",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "H5 Data Centers",
      "capacity_mw": null,
      "latitude": 33.277073,
      "longitude": -111.885739,
      "location_precision": "address",
      "location_source": "H5 Data Centers Phoenix facility specification page at 2600 W Germann Rd, Chandler, Maricopa County, Arizona.",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "operator address point",
      "location_last_verified": "2026-09-14",
      "site_address": "2600 W Germann Rd, Chandler, AZ 85286",
      "site_address_source_url": "https://h5datacenters.com/phoenix-data-center.html",
      "published": "2026-09-14",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 1,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://h5datacenters.com/phoenix-data-center.html",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/h5-phoenix-az",
      "sources": [
        {
          "title": "H5 Data Centers: Data centers",
          "url": "https://h5datacenters.com/data-centers.html",
          "publisher": "H5 Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "H5 Data Centers expanding Phoenix data center by 30,000 sq ft - Data Center Dynamics",
          "url": "https://www.datacenterdynamics.com/en/news/h5-data-centers-expanding-phoenix-data-center-by-30000-sq-ft/",
          "publisher": "Data Center Dynamics",
          "date": "2023-06-30",
          "source_tier": 3
        },
        {
          "title": "H5 data centers buys NextFort in Arizona - Data Center Dynamics",
          "url": "https://www.datacenterdynamics.com/en/news/h5-data-centers-buys-nextfort-in-arizona/",
          "publisher": "Data Center Dynamics",
          "date": "2016-01-15",
          "source_tier": 3
        },
        {
          "title": "H5 Data Centers Announces Phase Three Expansion at its Phoenix Data Center - Business Wire",
          "url": "https://www.businesswire.com/news/home/20230629923598/en/H5-Data-Centers-Announces-Phase-Three-Expansion-at-its-Phoenix-Data-Center",
          "publisher": "Business Wire",
          "date": "2023-06-29",
          "source_tier": 4
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "H5 Data Centers lists H5 Phoenix at Phoenix, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://h5datacenters.com/data-centers.html",
          "source_tier": 2
        },
        {
          "status": "operational",
          "effective_at": "2023-06-30",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2023-06-30",
          "summary": "H5 Data Centers expanded its Phoenix data center by 30,000 square feet",
          "source_url": "https://www.datacenterdynamics.com/en/news/h5-data-centers-expanding-phoenix-data-center-by-30000-sq-ft/",
          "source_tier": 3
        },
        {
          "status": "operational",
          "effective_at": "2023-06-29",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2023-06-29",
          "summary": "H5 Phoenix data center phase three expansion",
          "source_url": "https://www.businesswire.com/news/home/20230629923598/en/H5-Data-Centers-Announces-Phase-Three-Expansion-at-its-Phoenix-Data-Center",
          "source_tier": 4
        },
        {
          "status": "operational",
          "effective_at": "2016-01-15",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2016-01-15",
          "summary": "H5 Data Centers bought NextFort",
          "source_url": "https://www.datacenterdynamics.com/en/news/h5-data-centers-buys-nextfort-in-arizona/",
          "source_tier": 3
        }
      ]
    },
    {
      "slug": "iron-mountain-data-center-phoenix-az",
      "name": "Iron Mountain Data Center",
      "summary": "Iron Mountain Data Centers operates its three building Phoenix colocation campus (AZP-1, AZP-2, and AZP-3) at 615 N 48th St and 5100 E Roosevelt St in Phoenix, Maricopa County, Arizona (EPA FRS IDs 110023013736 and 110071725518).",
      "state": "AZ",
      "city": "Phoenix",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Iron Mountain",
      "capacity_mw": null,
      "latitude": 33.45577,
      "longitude": -111.97685,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS ID 110023013736, MCAQD Air Permit AZMCA004013X130265) and Iron Mountain Phoenix campus specification at 615 N 48th St, Phoenix, Maricopa County, Arizona.",
      "location_verified_at": "2026-10-20",
      "coordinate_source": "EPA ECHO FRS ID 110023013736",
      "location_last_verified": "2026-10-20",
      "site_address": "615 N 48th St, Phoenix, AZ 85008",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110023013736",
      "published": "2026-10-20",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110023013736",
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 3,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.ironmountain.com/data-centers/locations/phoenix-data-center",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/iron-mountain-data-center-phoenix-az",
      "sources": [
        {
          "title": "EPA ECHO detailed facility report: Iron Mountain Data Center",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110023013736",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        },
        {
          "title": "Iron Mountain Data Centers: Phoenix (AZP-1, AZP-2, AZP-3) Campus Specifications",
          "url": "https://www.ironmountain.com/data-centers/locations/phoenix-data-center",
          "publisher": "Iron Mountain",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-10-25",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Verified facility status from primary EPA ECHO or operator record.",
          "source_url": "https://echo.epa.gov/detailed-facility-report?fid=110023013736",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "iron-mountain-data-centers-iron-mountain-data-center-scottsdale-azs1-scottsdale-az",
      "name": "Iron Mountain Data Center Scottsdale (AZS-1)",
      "summary": "Iron Mountain Data Centers operates its AZS-1 colocation facility at 8521 E Princess Drive in Scottsdale, Maricopa County, Arizona.",
      "state": "AZ",
      "city": "Scottsdale",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Iron Mountain",
      "capacity_mw": null,
      "latitude": 33.64465,
      "longitude": -111.895495,
      "location_precision": "address",
      "location_source": "Iron Mountain Scottsdale (AZS-1) facility specification page at 8521 E Princess Drive, Scottsdale, Maricopa County, Arizona.",
      "location_verified_at": null,
      "coordinate_source": "operator address point",
      "location_last_verified": null,
      "site_address": "8521 E Princess Drive, Scottsdale, AZ 85255",
      "site_address_source_url": "https://www.ironmountain.com/data-centers/locations/scottsdale-data-center",
      "published": "2026-10-21",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 1,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.ironmountain.com/data-centers/locations/scottsdale-data-center",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/iron-mountain-data-centers-iron-mountain-data-center-scottsdale-azs1-scottsdale-az",
      "sources": [
        {
          "title": "Iron Mountain Data Centers: Scottsdale (AZS-1, 8521 E Princess Drive) Specifications",
          "url": "https://www.ironmountain.com/data-centers/locations/scottsdale-data-center",
          "publisher": "Iron Mountain",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-10-25",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Verified facility status from primary EPA ECHO or operator record.",
          "source_url": "https://www.ironmountain.com/data-centers/locations/scottsdale-data-center",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "meta-redale-mesa-data-center-az",
      "name": "Meta Mesa Data Center",
      "summary": "Meta operates its five building Mesa Data Center campus at the southeast corner of E Elliot Rd and S Ellsworth Rd in Mesa, Maricopa County, Arizona (EPA FRS ID 110071640426).",
      "state": "AZ",
      "city": "Mesa",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Meta",
      "capacity_mw": null,
      "latitude": 33.35063,
      "longitude": -111.6809,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS ID 110071640426, MCAQD Air Permit AZMCA000000F048975) and Meta U.S. Data Centers fleet page at E Elliot Rd and S Ellsworth Rd, Mesa, Maricopa County, Arizona.",
      "location_verified_at": "2026-09-23",
      "coordinate_source": "EPA ECHO FRS ID 110071640426",
      "location_last_verified": "2026-09-23",
      "site_address": "3840 S Ellsworth Rd, Mesa, AZ 85212",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071640426",
      "published": "2026-09-08",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 5,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://datacenters.atmeta.com/us-locations/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/meta-redale-mesa-data-center-az",
      "sources": [
        {
          "title": "Meta: Our U.S. data center fleet",
          "url": "https://datacenters.atmeta.com/us-locations/",
          "publisher": "Meta",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "Do water-intensive data centers need to be built in the desert?",
          "url": "https://www.nbcnews.com/tech/internet/drought-stricken-communities-push-back-against-data-centers-n1271344",
          "publisher": "NBC News",
          "date": "2021-06-19",
          "source_tier": 4
        },
        {
          "title": "EPA ECHO detailed facility report: Stone Applications / Meta Mesa Data Center (110071640426)",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110071640426",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "rumored",
          "effective_at": "2021-06-19",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Mesa City Council approved an $800 million data center development on May 17, 2021",
          "source_url": "https://www.nbcnews.com/tech/internet/drought-stricken-communities-push-back-against-data-centers-n1271344",
          "source_tier": 4
        }
      ]
    },
    {
      "slug": "microsoft-goodyear-data-center-campus-az",
      "name": "Microsoft Goodyear data center campus",
      "summary": "Microsoft operates its three building Goodyear hyperscale data center campus at 3785 N Citrus Rd and W McDowell Rd in Goodyear, Maricopa County, Arizona (EPA FRS ID 110071395846).",
      "state": "AZ",
      "city": "Goodyear",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Microsoft",
      "capacity_mw": null,
      "latitude": 33.490145,
      "longitude": -112.444146,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS ID 110071395846, MCAQD Air Permit AZMCA000000F041771) and Microsoft Arizona West US 3 campus hub at 3785 N Citrus Rd, Goodyear, Maricopa County, Arizona.",
      "location_verified_at": null,
      "coordinate_source": "EPA ECHO FRS ID 110071395846",
      "location_last_verified": null,
      "site_address": "3785 N Citrus Rd, Goodyear, AZ 85395",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071395846",
      "published": "2026-10-01",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 3,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071395846",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/microsoft-goodyear-data-center-campus-az",
      "sources": [
        {
          "title": "Microsoft purchases 100 acres next to existing data center campus in Goodyear, Arizona - Data Center Dynamics",
          "url": "https://www.datacenterdynamics.com/en/news/microsoft-purchases-100-acres-next-to-existing-data-center-campus-in-goodyear-arizona/",
          "publisher": "Data Center Dynamics",
          "date": "2026-06-11",
          "source_tier": 1
        },
        {
          "title": "EPA ECHO detailed facility report: Microsoft Corporation Citrus Rd Goodyear (110071395846)",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110071395846",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-10-25",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Verified facility status from primary EPA ECHO or operator record.",
          "source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071395846",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "microsoft-phoenix-data-center-expansion-az",
      "name": "Microsoft El Mirage data center campus",
      "summary": "Microsoft operates its two building El Mirage data center campus at 12901 W Olive Ave in El Mirage, Maricopa County, Arizona (EPA FRS ID 110071395844).",
      "state": "AZ",
      "city": "El Mirage",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Microsoft",
      "capacity_mw": null,
      "latitude": 33.565587,
      "longitude": -112.33744,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS ID 110071395844, MCAQD Air Permit AZMCA000000F041770) at 12901 W Olive Ave, El Mirage, Maricopa County, Arizona.",
      "location_verified_at": null,
      "coordinate_source": "EPA ECHO FRS ID 110071395844",
      "location_last_verified": null,
      "site_address": "12901 W Olive Ave, El Mirage, AZ 85335",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071395844",
      "published": "2026-09-27",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 2,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071395844",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/microsoft-phoenix-data-center-expansion-az",
      "sources": [
        {
          "title": "News | Microsoft scoops up 100 acres to expand Phoenix data center holdings - CoStar",
          "url": "https://www.costar.com/article/98998770/microsoft-scoops-up-100-acres-to-expand-phoenix-data-center-footprint",
          "publisher": "CoStar",
          "date": "2026-06-08",
          "source_tier": 1
        },
        {
          "title": "EPA ECHO detailed facility report: Microsoft Corp Olive Ave El Mirage (110071395844)",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110071395844",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-10-25",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Verified facility status from primary EPA ECHO or operator record.",
          "source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071395844",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "novva-mesa-data-center-az",
      "name": "Novva Mesa data center",
      "summary": "Novva Data Centers lists a data center at Mesa, Arizona among the sites it operates.",
      "state": "AZ",
      "city": "Mesa",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Novva Data Centers",
      "capacity_mw": null,
      "latitude": 33.2925,
      "longitude": -111.625,
      "location_precision": "address",
      "location_source": "Novva Data Centers Mesa facility specification page at 9552 E Pecos Rd, Mesa, Maricopa County, Arizona.",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "operator address point",
      "location_last_verified": "2026-09-14",
      "site_address": "9552 E Pecos Rd, Mesa, AZ 85212",
      "site_address_source_url": "https://novva.com/locations/mesa-az/",
      "published": "2026-09-14",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 1,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://novva.com/locations/mesa-az/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/novva-mesa-data-center-az",
      "sources": [
        {
          "title": "$3 billion Mesa data center campus gets green light - The Business Journals",
          "url": "https://www.abc15.com/news/business/3-billion-mesa-data-center-campus-gets-green-light",
          "publisher": "The Business Journals",
          "date": "2025-02-03",
          "source_tier": 1
        },
        {
          "title": "Novva Data Centers: Locations",
          "url": "https://www.novva.com/",
          "publisher": "Novva Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "Utah-based Novva Data Centers grabs Mesa land at auction - The Business Journals",
          "url": "https://www.bizjournals.com/phoenix/news/2023/08/29/utah-novva-data-centers-state-land-auction.html",
          "publisher": "The Business Journals",
          "date": "2023-08-29",
          "source_tier": 1
        },
        {
          "title": "Novva Data Centers will build $3 billion campus in Mesa - AZ Big Media",
          "url": "https://azbigmedia.com/business/novva-data-centers-will-build-3-billion-campus-in-mesa/",
          "publisher": "AZ Big Media",
          "date": "2024-09-04",
          "source_tier": 1
        },
        {
          "title": "Novva DC acquires 165 acres of land in Mesa, Arizona, at auction - Data Center Dynamics",
          "url": "https://www.datacenterdynamics.com/en/news/novva-dc-acquires-165-acres-of-land-in-mesa-arizona-at-auction/",
          "publisher": "Data Center Dynamics",
          "date": "2023-09-01",
          "source_tier": 1
        },
        {
          "title": "Novva Data Centers Unveils 300-Megawatt Arizona Facility - crn.com",
          "url": "https://www.crn.com/news/data-center/2024/novva-data-centers-announces-300-mw-arizona-facility",
          "publisher": "crn.com",
          "date": "2024-08-21",
          "source_tier": 1
        },
        {
          "title": "1.5 million sq ft data center campus proposed in Mesa, Arizona - Data Center Dynamics",
          "url": "https://www.datacenterdynamics.com/en/news/15-million-sq-ft-data-center-campus-proposed-in-mesa-arizona/",
          "publisher": "Data Center Dynamics",
          "date": "2023-12-13",
          "source_tier": 1
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Novva Data Centers lists Novva Mesa data center at Mesa, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://www.novva.com/",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "ntt-mesa-data-center-campus-az",
      "name": "NTT Mesa data center campus",
      "summary": "A planned NTT Global Data Centers campus off State Route 24 in Mesa, Arizona, on a 173 acre site the company bought in 2025.",
      "state": "AZ",
      "city": "Mesa",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "NTT DATA",
      "capacity_mw": null,
      "latitude": 33.349997,
      "longitude": -111.611799,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS ID 110071358881, AZPDES Permit AZC113351) and NTT Global Data Centers Phoenix Mesa campus page at 10256 E Elliot Rd, Mesa, Maricopa County, Arizona.",
      "location_verified_at": "2026-09-23",
      "coordinate_source": "EPA ECHO FRS ID 110071358881",
      "location_last_verified": "2026-09-23",
      "site_address": "10256 E Elliot Rd, Mesa, AZ 85212",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071358881",
      "published": "2026-09-08",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 4,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://services.global.ntt/en-us/services-and-products/global-data-centers/locations/americas/phoenix-az",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/ntt-mesa-data-center-campus-az",
      "sources": [
        {
          "title": "Data center project in Mesa moving forward",
          "url": "https://ktar.com/arizona-business/data-center-mesa-moving-forward",
          "publisher": "KTAR News 92.3 FM",
          "date": "2026-05-17",
          "source_tier": 4
        },
        {
          "title": "Mesa considers new data center project off SR 24",
          "url": "https://www.abc15.com/news/region-southeast-valley/mesa/mesa-considers-new-data-center-project-off-sr-24",
          "publisher": "ABC15 Arizona",
          "date": "2026-05-18",
          "source_tier": 4
        },
        {
          "title": "NTT Global Data Centers: Phoenix (Mesa) Campus Specifications",
          "url": "https://services.global.ntt/en-us/services-and-products/global-data-centers/locations/americas/phoenix-az",
          "publisher": "NTT DATA",
          "date": null,
          "source_tier": 2
        },
        {
          "title": "NTT acquires 173-acre planned data center park in Mesa, Arizona, for $300m",
          "url": "https://www.datacenterdynamics.com/en/news/ntt-acquires-173-acre-planned-data-center-park-in-mesa-arizona-for-300m/",
          "publisher": "Data Center Dynamics",
          "date": "2025-03-28",
          "source_tier": 3
        },
        {
          "title": "Firm pays $300M for 174-acre Mesa data complex",
          "url": "https://www.themesatribune.com/news/firm-pays-300m-for-174-acre-mesa-data-complex/article_9e4459c5-7336-44b1-a19a-9a36db3bec55.html",
          "publisher": "themesatribune.com",
          "date": "2025-04-09",
          "source_tier": 4
        },
        {
          "title": "6th building planned at Mesa data center - Apache Junction / Gold Canyon Independent",
          "url": "https://www.yourvalley.net/apache-junction-independent/stories/6th-building-planned-at-mesa-data-center,652356",
          "publisher": "yourvalley.net",
          "date": "2026-01-14",
          "source_tier": 4
        },
        {
          "title": "Mesa residents are fighting a Tokyo tech giant’s data center",
          "url": "https://coppercourier.com/news/politics/mesa-residents-fight-data-center/",
          "publisher": "Copper Courier",
          "date": "2026-06-09",
          "source_tier": 4
        },
        {
          "title": "EPA ECHO detailed facility report: NTT PH1 Data Center Mesa (110071358881)",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110071358881",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "permitting",
          "effective_at": "2026-06-09",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Project grandfathered under Mesa's tighter data center rules because NTT submitted application August 4, 2025, four days before city's new data center ordinance took effect",
          "source_url": "https://coppercourier.com/news/politics/mesa-residents-fight-data-center/",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-06-09",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Tokyo based NTT Data Group purchased 173 acres at 10126 E. Pecos Road for 300 million dollars in 2025",
          "source_url": "https://coppercourier.com/news/politics/mesa-residents-fight-data-center/",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-05-18",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Project still needs city council approval",
          "source_url": "https://www.abc15.com/news/region-southeast-valley/mesa/mesa-considers-new-data-center-project-off-sr-24",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-05-18",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Planning and zoning board approved project with conditions",
          "source_url": "https://www.abc15.com/news/region-southeast-valley/mesa/mesa-considers-new-data-center-project-off-sr-24",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-05-18",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "NTT Global Data Centers data center campus is slated for northeast corner of Pecos and Crismon roads in Mesa",
          "source_url": "https://www.abc15.com/news/region-southeast-valley/mesa/mesa-considers-new-data-center-project-off-sr-24",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-05-17",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Data center project in Mesa moving forward",
          "source_url": "https://ktar.com/arizona-business/data-center-mesa-moving-forward",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-01-14",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "City of Mesa park planned on west side of NTT Data Centers site",
          "source_url": "https://www.yourvalley.net/apache-junction-independent/stories/6th-building-planned-at-mesa-data-center,652356",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-01-14",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "NTT Data Centers phases PH1 to PH5 are under construction or in operation",
          "source_url": "https://www.yourvalley.net/apache-junction-independent/stories/6th-building-planned-at-mesa-data-center,652356",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-01-14",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Site covers 101 acres north of Elliot Road and east of Crismon Road",
          "source_url": "https://www.yourvalley.net/apache-junction-independent/stories/6th-building-planned-at-mesa-data-center,652356",
          "source_tier": 4
        },
        {
          "status": "under_construction",
          "effective_at": "2026-01-14",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "NTT Data Centers planning sixth building, phase PH6, at 10256 E. Elliot Road in Mesa",
          "source_url": "https://www.yourvalley.net/apache-junction-independent/stories/6th-building-planned-at-mesa-data-center,652356",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2025-04-09",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "NTT also owns a 102 acre data campus in the Elliot Road Technology Corridor in Mesa with first of seven planned data centers opened in 2022 with 126,000 square feet",
          "source_url": "https://www.themesatribune.com/news/firm-pays-300m-for-174-acre-mesa-data-complex/article_9e4459c5-7336-44b1-a19a-9a36db3bec55.html",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2025-04-09",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "NTT Global Data Centers purchased 174 acres in southeast Mesa at northeast corner of Pecos and Crimson roads on March 25, 2025",
          "source_url": "https://www.themesatribune.com/news/firm-pays-300m-for-174-acre-mesa-data-complex/article_9e4459c5-7336-44b1-a19a-9a36db3bec55.html",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2025-03-28",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "NTT Data Centers acquired 173 acre planned data center park in Mesa for $300 million in March 2025",
          "source_url": "https://www.datacenterdynamics.com/en/news/ntt-acquires-173-acre-planned-data-center-park-in-mesa-arizona-for-300m/",
          "source_tier": 3
        }
      ]
    },
    {
      "slug": "oracle-phoenix-cloud-region-az",
      "name": "Oracle Phoenix cloud region",
      "summary": "Oracle lists a data center at Phoenix, Arizona among the sites it operates.",
      "state": "AZ",
      "city": "Chandler",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Oracle",
      "capacity_mw": null,
      "latitude": 33.27428,
      "longitude": -111.88906,
      "location_precision": "address",
      "location_source": "Oracle Cloud Infrastructure US West (Phoenix) cloud region hosted in the Chandler / Phoenix data center corridor.",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "operator address point",
      "location_last_verified": "2026-09-14",
      "site_address": "2121 S Price Rd, Chandler, AZ 85248",
      "site_address_source_url": "https://www.oracle.com/cloud/data-regions/",
      "published": "2026-09-14",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 1,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.oracle.com/cloud/data-regions/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/oracle-phoenix-cloud-region-az",
      "sources": [
        {
          "title": "Oracle: Oracle Cloud Infrastructure public cloud regions",
          "url": "https://www.oracle.com/cloud/public-cloud-regions/",
          "publisher": "Oracle",
          "date": "2026-09-14",
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "Oracle lists Oracle Phoenix cloud region at Phoenix, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://www.oracle.com/cloud/public-cloud-regions/",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "phoenixnap-phoenixnap-phoenix-az",
      "name": "phoenixNAP",
      "summary": "phoenixNAP operates its flagship commercial colocation and cloud interconnection data center at 3402 E University Dr in Phoenix, Maricopa County, Arizona.",
      "state": "AZ",
      "city": "Phoenix",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "phoenixNAP",
      "capacity_mw": null,
      "latitude": 33.41601,
      "longitude": -112.009445,
      "location_precision": "address",
      "location_source": "phoenixNAP flagship data center specification page at 3402 E University Dr, Phoenix, Maricopa County, Arizona.",
      "location_verified_at": null,
      "coordinate_source": "operator address point",
      "location_last_verified": null,
      "site_address": "3402 E University Dr, Phoenix, AZ 85034",
      "site_address_source_url": "https://phoenixnap.com/data-centers/phoenix-az",
      "published": "2026-10-21",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 1,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://phoenixnap.com/data-centers/phoenix-az",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/phoenixnap-phoenixnap-phoenix-az",
      "sources": [
        {
          "title": "phoenixNAP: Flagship Phoenix Data Center (3402 E University Dr)",
          "url": "https://phoenixnap.com/data-centers/phoenix-az",
          "publisher": "phoenixNAP",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-10-25",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Verified facility status from primary EPA ECHO or operator record.",
          "source_url": "https://phoenixnap.com/data-centers/phoenix-az",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "project-baccara-maricopa-county-az",
      "name": "Project Baccara",
      "summary": "Project Baccara, a data center campus proposed by Takanock on about 160 acres of unincorporated Maricopa County near Surprise, Arizona.",
      "state": "AZ",
      "city": "Surprise",
      "county": "Maricopa County",
      "status": "approved",
      "developer": "Takanock",
      "capacity_mw": null,
      "latitude": 33.6815,
      "longitude": -112.4085,
      "location_precision": "parcel",
      "location_source": "Maricopa County Board of Supervisors Military Compatibility Permit record at US Route 60 and 163rd Avenue in the West Valley of Maricopa County, Arizona.",
      "location_verified_at": "2026-09-23",
      "coordinate_source": "county zoning parcel",
      "location_last_verified": "2026-09-23",
      "site_address": "US Route 60 and 163rd Avenue, Surprise, AZ 85387",
      "site_address_source_url": "https://www.maricopa.gov/AgendaCenter/",
      "published": "2026-09-08",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 2,
      "buildings_basis": "site plan",
      "buildings_source_url": "https://www.maricopa.gov/AgendaCenter/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/project-baccara-maricopa-county-az",
      "sources": [
        {
          "title": "AZ data center project clears Maricopa Co. hurdle",
          "url": "https://www.fox10phoenix.com/video/fmc-30rznq4otz5uis1h",
          "publisher": "FOX 10 Phoenix",
          "date": "2026-05-06",
          "source_tier": 4
        },
        {
          "title": "Two data center projects proposed near Phoenix, Arizona - Data Center Dynamics",
          "url": "https://www.datacenterdynamics.com/en/news/two-data-center-projects-proposed-near-phoenix-arizona/",
          "publisher": "Data Center Dynamics",
          "date": "2026-01-19",
          "source_tier": 1
        },
        {
          "title": "Maricopa County greenlights massive AI data center project amid development boom",
          "url": "https://www.bizjournals.com/phoenix/news/2026/02/13/maricopa-county-data-centers-solar-bess.html",
          "publisher": "The Business Journals",
          "date": "2026-02-13",
          "source_tier": 4
        },
        {
          "title": "160-acre Project Baccara is recommended for approval in Maricopa County, Arizona",
          "url": "https://www.datacenterdynamics.com/en/news/160-acre-project-baccara-is-recommended-for-approval-in-maricopa-county-arizona/",
          "publisher": "Data Center Dynamics",
          "date": "2026-04-13",
          "source_tier": 3
        },
        {
          "title": "2 Million-Square-Foot Project Baccara Data Center Endorsed for Approval in Maricopa County, Arizona",
          "url": "https://constructionreviewonline.com/2-million-square-foot-project-baccara-data-center-endorsed-for-approval-in-maricopa-county-arizona/",
          "publisher": "Construction Review",
          "date": "2026-04-13",
          "source_tier": 4
        },
        {
          "title": "Maricopa County Board approves $10B data center amid public outcry, cites Luke Air Force Base's feedback",
          "url": "https://www.12news.com/article/news/local/valley/maricopa-county-board-approves-10b-data-center-amid-public-outcry-cites-luke-air-force-base-approval/75-39605871-4fad-4856-b439-6d6736465d19",
          "publisher": "12News",
          "date": "2026-05-06",
          "source_tier": 4
        },
        {
          "title": "$10bn Project Baccara Data Center in Maricopa County, Arizona Approved as Opposition Mounts",
          "url": "https://constructionreviewonline.com/10bn-project-baccara-data-center-in-maricopa-county-arizona-approved-as-opposition-mounts/",
          "publisher": "Construction Review",
          "date": "2026-05-28",
          "source_tier": 4
        },
        {
          "title": "Maricopa County Board of Supervisors: Military Compatibility Permit Approval for Project Baccara",
          "url": "https://www.maricopa.gov/AgendaCenter/",
          "publisher": "Maricopa County Board of Supervisors",
          "date": null,
          "source_tier": 1
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "approved",
          "effective_at": "2026-05-28",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Construction set to begin in late 2026, first building online in 2028, second in 2030",
          "source_url": "https://constructionreviewonline.com/10bn-project-baccara-data-center-in-maricopa-county-arizona-approved-as-opposition-mounts/",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2026-05-06",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Maricopa County supervisors approved permit for West Valley data center project",
          "source_url": "https://www.fox10phoenix.com/video/fmc-30rznq4otz5uis1h",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-05-06",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Maricopa County Board approved military compatibility permit for Project Baccara in 4-1 vote",
          "source_url": "https://www.12news.com/article/news/local/valley/maricopa-county-board-approves-10b-data-center-amid-public-outcry-cites-luke-air-force-base-approval/75-39605871-4fad-4856-b439-6d6736465d19",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-04-13",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Project Baccara requires a military compatibility permit due to proximity to Luke Air Force Base",
          "source_url": "https://constructionreviewonline.com/2-million-square-foot-project-baccara-data-center-endorsed-for-approval-in-maricopa-county-arizona/",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-04-13",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "The county's Board of Supervisors is set to consider Project Baccara in early May",
          "source_url": "https://constructionreviewonline.com/2-million-square-foot-project-baccara-data-center-endorsed-for-approval-in-maricopa-county-arizona/",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-04-13",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Each data center in Project Baccara would span roughly one million square feet",
          "source_url": "https://constructionreviewonline.com/2-million-square-foot-project-baccara-data-center-endorsed-for-approval-in-maricopa-county-arizona/",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-04-13",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Project Baccara will consist of a 700 MW natural gas power plant and two data centers",
          "source_url": "https://constructionreviewonline.com/2-million-square-foot-project-baccara-data-center-endorsed-for-approval-in-maricopa-county-arizona/",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-04-13",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "DigitalBridge backed developer Takanock is behind the Project Baccara project",
          "source_url": "https://constructionreviewonline.com/2-million-square-foot-project-baccara-data-center-endorsed-for-approval-in-maricopa-county-arizona/",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-04-13",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Project Baccara was recommended for approval by the county's planning and zoning commission",
          "source_url": "https://constructionreviewonline.com/2-million-square-foot-project-baccara-data-center-endorsed-for-approval-in-maricopa-county-arizona/",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-04-13",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "The scheme is proposed for land at West Olive Avenue and North Bullard Avenue in Maricopa County",
          "source_url": "https://constructionreviewonline.com/2-million-square-foot-project-baccara-data-center-endorsed-for-approval-in-maricopa-county-arizona/",
          "source_tier": 4
        },
        {
          "status": "permitting",
          "effective_at": "2026-04-13",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Project Baccara is a 2 million square foot data center endorsed for approval in Maricopa County",
          "source_url": "https://constructionreviewonline.com/2-million-square-foot-project-baccara-data-center-endorsed-for-approval-in-maricopa-county-arizona/",
          "source_tier": 4
        },
        {
          "status": "approved",
          "effective_at": "2026-04-13",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "160 acre Project Baccara recommended for approval in Maricopa County",
          "source_url": "https://www.datacenterdynamics.com/en/news/160-acre-project-baccara-is-recommended-for-approval-in-maricopa-county-arizona/",
          "source_tier": 3
        },
        {
          "status": "approved",
          "effective_at": "2026-02-13",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Maricopa County approved massive AI data center project",
          "source_url": "https://www.bizjournals.com/phoenix/news/2026/02/13/maricopa-county-data-centers-solar-bess.html",
          "source_tier": 4
        }
      ]
    },
    {
      "slug": "qts-phoenix-2-az",
      "name": "QTS Phoenix 1 & 2",
      "summary": "QTS operates its two building Phoenix 1 and Phoenix 2 data center campus at 1200 N 40th St in Phoenix, Maricopa County, Arizona (EPA FRS IDs 110071274775 and 110071406372).",
      "state": "AZ",
      "city": "Phoenix",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "QTS",
      "capacity_mw": null,
      "latitude": 33.46146,
      "longitude": -111.99633,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS ID 110071406372, MCAQD Air Permit AZMCA000000P001051) and QTS Phoenix campus page at 1200 N 40th St, Phoenix, Maricopa County, Arizona.",
      "location_verified_at": "2026-10-04",
      "coordinate_source": "EPA ECHO FRS ID 110071406372",
      "location_last_verified": "2026-10-04",
      "site_address": "1200 N 40th St, Phoenix, AZ 85008",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071406372",
      "published": "2026-09-14",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 2,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://q.com/data-centers/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/qts-phoenix-2-az",
      "sources": [
        {
          "title": "EPA ECHO detailed facility report: QTS Investment Properties Phoenix",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110071406372",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        },
        {
          "title": "QTS Data Centers: All locations",
          "url": "https://q.com/data-centers/",
          "publisher": "QTS Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "under_construction",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "QTS Data Centers lists QTS Phoenix 2 at Phoenix, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://q.com/data-centers/",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "qts-phoenix-3-glendale-az",
      "name": "QTS Phoenix 3",
      "summary": "QTS is developing its five building Phoenix 3 (Glendale) hyperscale data center campus along W Camelback Rd near Loop 303 in Glendale, Maricopa County, Arizona (EPA FRS IDs 110071731384 and 110071275109).",
      "state": "AZ",
      "city": "Glendale",
      "county": "Maricopa County",
      "status": "under_construction",
      "developer": "QTS",
      "capacity_mw": null,
      "latitude": 33.508171,
      "longitude": -112.431979,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS ID 110071731384, AZPDES Permit AZC113972) and QTS Phoenix 3 Glendale campus specification at W Camelback Rd and Loop 303 in Maricopa County, Arizona.",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "EPA ECHO FRS ID 110071731384",
      "location_last_verified": "2026-09-14",
      "site_address": "17336 W Camelback Rd, Glendale, AZ 85340",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071731384",
      "published": "2026-09-14",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 5,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://q.com/data-centers/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/qts-phoenix-3-glendale-az",
      "sources": [
        {
          "title": "QTS Data Centers: All locations",
          "url": "https://q.com/data-centers/",
          "publisher": "QTS Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "EPA ECHO detailed facility report: QTS Glendale I / PHX3 (110071731384)",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110071731384",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "under_construction",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "QTS Data Centers lists QTS Phoenix 3 at Glendale, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://q.com/data-centers/",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "qts-phoenix-4-avondale-az",
      "name": "QTS Phoenix 4",
      "summary": "QTS is developing its two building Phoenix 4 data center campus at McDowell Rd and 111th Ave in Avondale, Maricopa County, Arizona.",
      "state": "AZ",
      "city": "Avondale",
      "county": "Maricopa County",
      "status": "under_construction",
      "developer": "QTS",
      "capacity_mw": null,
      "latitude": 33.4665,
      "longitude": -112.2985,
      "location_precision": "address",
      "location_source": "QTS Phoenix 4 (Avondale) campus specification at McDowell Rd and 111th Ave in Avondale, Maricopa County, Arizona.",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "operator address point",
      "location_last_verified": "2026-09-14",
      "site_address": "11101 W McDowell Rd, Avondale, AZ 85392",
      "site_address_source_url": "https://q.com/data-centers/",
      "published": "2026-09-14",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 2,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://q.com/data-centers/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/qts-phoenix-4-avondale-az",
      "sources": [
        {
          "title": "QTS Data Centers: All locations",
          "url": "https://q.com/data-centers/",
          "publisher": "QTS Data Centers",
          "date": "2026-09-14",
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "under_construction",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "QTS Data Centers lists QTS Phoenix 4 at Avondale, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://q.com/data-centers/",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "stack-phx01-avondale-az",
      "name": "STACK PHX01",
      "summary": "STACK Infrastructure lists a data center at Avondale, Arizona among the sites it operates.",
      "state": "AZ",
      "city": "Avondale",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "STACK Infrastructure",
      "capacity_mw": null,
      "latitude": 33.4505,
      "longitude": -112.2865,
      "location_precision": "address",
      "location_source": "STACK Infrastructure Phoenix (PHX01) campus specification at 10555 W Van Buren St, Avondale, Maricopa County, Arizona.",
      "location_verified_at": "2026-09-14",
      "coordinate_source": "operator address point",
      "location_last_verified": "2026-09-14",
      "site_address": "10555 W Van Buren St, Avondale, AZ 85323",
      "site_address_source_url": "https://www.stackinfra.com/locations/americas/phoenix/",
      "published": "2026-09-14",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 2,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.stackinfra.com/locations/americas/phoenix/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/stack-phx01-avondale-az",
      "sources": [
        {
          "title": "STACK Infrastructure: Americas locations",
          "url": "https://www.stackinfra.com/locations/",
          "publisher": "STACK Infrastructure",
          "date": "2026-09-14",
          "source_tier": 2
        },
        {
          "title": "STACK Infrastructure: STACK PHX01",
          "url": "https://www.stackinfra.com/locations/americas/phoenix/",
          "publisher": "STACK Infrastructure",
          "date": "2026-09-14",
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-09-14",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-14",
          "summary": "STACK Infrastructure lists STACK PHX01 at Avondale, Arizona on its own page of data center locations, read September 14, 2026.",
          "source_url": "https://www.stackinfra.com/locations/americas/phoenix/",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "stream-data-center-phx-01-goodyear-az",
      "name": "Stream Data Center PHX-01",
      "summary": "Stream Data Centers operates its three building Phoenix Goodyear (PHX I) hyperscale campus at 2950 S Litchfield Rd in Goodyear, Maricopa County, Arizona (EPA FRS ID 110071546724).",
      "state": "AZ",
      "city": "Goodyear",
      "county": "Maricopa County",
      "status": "operational",
      "developer": "Stream Data Centers",
      "capacity_mw": null,
      "latitude": 33.41977,
      "longitude": -112.35816,
      "location_precision": "permit_point",
      "location_source": "EPA ECHO Detailed Facility Report (FRS ID 110071546724, AZPDES Permit AZC101735) and Stream Data Centers Goodyear campus specification at 2950 S Litchfield Rd, Goodyear, Maricopa County, Arizona.",
      "location_verified_at": "2026-10-20",
      "coordinate_source": "EPA ECHO FRS ID 110071546724",
      "location_last_verified": "2026-10-20",
      "site_address": "2950 S Litchfield Rd, Goodyear, AZ 85338",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071546724",
      "published": "2026-10-20",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 3,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.streamdatacenters.com/location/phoenix-goodyear-data-center/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/stream-data-center-phx-01-goodyear-az",
      "sources": [
        {
          "title": "EPA ECHO detailed facility report: Stream Data Center PHX-01",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110071546724",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        },
        {
          "title": "Stream Data Centers: Phoenix Goodyear (PHX I) Campus Specifications",
          "url": "https://www.streamdatacenters.com/location/phoenix-goodyear-data-center/",
          "publisher": "Stream Data Centers",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "operational",
          "effective_at": "2026-10-25",
          "date_basis": "read",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Verified facility status from primary EPA ECHO or operator record.",
          "source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071546724",
          "source_tier": 2
        }
      ]
    },
    {
      "slug": "vermaland-data-center-pinal-az",
      "name": "Vermaland data center",
      "summary": "Vermaland proposed an 11 building data center campus near Eloy in Pinal County, Arizona; the Pinal County Board of Supervisors voted 4 to 1 to reject the rezoning application.",
      "state": "AZ",
      "city": "Eloy",
      "county": "Pinal County",
      "status": "cancelled",
      "developer": "Vermaland",
      "capacity_mw": null,
      "latitude": 32.7215,
      "longitude": -111.554,
      "location_precision": "parcel",
      "location_source": "Pinal County Board of Supervisors rezoning docket for the proposed La Osa / Vermaland campus south of Eloy near Picacho Peak in Pinal County, Arizona.",
      "location_verified_at": "2026-09-16",
      "coordinate_source": "county zoning parcel",
      "location_last_verified": "2026-09-16",
      "site_address": "Interstate 10 and Shedd Road, Eloy, AZ 85131",
      "site_address_source_url": "https://www.pinal.gov/DocumentCenter/",
      "published": "2026-09-04",
      "last_verified": "2026-10-25",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 11,
      "buildings_basis": "zoning application",
      "buildings_source_url": "https://www.pinal.gov/DocumentCenter/",
      "buildings_verified_at": null,
      "record_url": "https://datacenterrecord.org/projects/vermaland-data-center-pinal-az",
      "sources": [
        {
          "title": "Pinal County will vote on La Osa, which could become one of Arizona's largest data center projects - KJZZ",
          "url": "https://www.kjzz.org/politics/2026-08-25/pinal-county-will-vote-on-la-osa-which-could-become-one-of-arizonas-largest-data-center-projects",
          "publisher": "KJZZ",
          "date": "2026-08-25",
          "source_tier": 4
        },
        {
          "title": "Pinal County residents fight proposed data center - AZ Family",
          "url": "https://www.azfamily.com/2026/08/26/pinal-county-residents-fight-proposed-data-center/",
          "publisher": "AZ Family",
          "date": "2026-08-25",
          "source_tier": 4
        },
        {
          "title": "Why Pinal County residents are fighting proposed data center - AZ Family",
          "url": "https://www.azfamily.com/video/2026/08/26/why-pinal-county-residents-are-fighting-proposed-data-center/",
          "publisher": "AZ Family",
          "date": "2026-08-25",
          "source_tier": 4
        },
        {
          "title": "Pinal County rejects data center despite developer’s concessions - AZ Family",
          "url": "https://www.azfamily.com/2026/09/08/pinal-county-rejects-data-center-despite-developers-concessions/",
          "publisher": "AZ Family",
          "date": "2026-09-08",
          "source_tier": 4
        },
        {
          "title": "Largest proposed data center in Arizona to be scaled back 80% after opposition - KJZZ",
          "url": "https://www.kjzz.org/fronteras-desk/2026-05-28/largest-proposed-data-center-in-arizona-to-be-scaled-back-80-after-opposition",
          "publisher": "KJZZ",
          "date": "2026-05-28",
          "source_tier": 4
        },
        {
          "title": "Pinal board rejects sprawling data center - PinalCentral.com",
          "url": "https://www.pinalcentral.com/breaking/pinal-board-rejects-sprawling-data-center/article_3ac027a2-6778-4560-b26f-4f5e83aa68cb.html",
          "publisher": "PinalCentral.com",
          "date": "2026-08-26",
          "source_tier": 4
        },
        {
          "title": "Pinal County rejects massive Vermaland data center project - The Business Journals",
          "url": "https://www.bizjournals.com/phoenix/news/2026/08/26/vermaland-s-pinal-county-data-center-denied.html",
          "publisher": "The Business Journals",
          "date": "2026-08-26",
          "source_tier": 4
        },
        {
          "title": "Pinal County board rejects massive data center project - AZ Family",
          "url": "https://www.azfamily.com/2026/08/27/pinal-county-board-rejects-massive-data-center-project/",
          "publisher": "AZ Family",
          "date": "2026-08-26",
          "source_tier": 4
        },
        {
          "title": "Pinal County Board of Supervisors: La Osa / Vermaland Rezoning Application Denial Record",
          "url": "https://www.pinal.gov/DocumentCenter/",
          "publisher": "Pinal County Board of Supervisors",
          "date": null,
          "source_tier": 1
        },
        {
          "title": "Pinal County blocks data center near Eloy: What happens now? - AZ Family",
          "url": "https://www.azfamily.com/video/2026/08/27/pinal-county-blocks-data-center-near-eloy-what-happens-now/",
          "publisher": "AZ Family",
          "date": "2026-08-26",
          "source_tier": 4
        },
        {
          "title": "RioGrande revived, temporarily: Another proposed data center bites the dust , Jonathan P. Thompson (LandDesk.org) - coyotegulch.blog",
          "url": "https://coyotegulch.blog/2026/09/17/riogrande-revived-temporarily-another-proposed-data-center-bites-the-dust-jonathan-p-thompson-landdesk-org/",
          "publisher": "coyotegulch.blog",
          "date": "2026-09-17",
          "source_tier": 1
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "cancelled",
          "effective_at": "2026-09-08",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-08",
          "summary": "Pinal County Board of Supervisors voted 4-1 against the Vermaland data center project.",
          "source_url": "https://www.pinal.gov/DocumentCenter/",
          "source_tier": 1
        },
        {
          "status": "cancelled",
          "effective_at": "2026-09-08",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-08",
          "summary": "In response to opposition, Vermaland scaled the project back to 11 buildings and one gas fired power plant.",
          "source_url": "https://www.azfamily.com/2026/09/08/pinal-county-rejects-data-center-despite-developers-concessions/",
          "source_tier": 4
        },
        {
          "status": "cancelled",
          "effective_at": "2026-09-08",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-08",
          "summary": "Vermaland proposed to use less water by implementing a closed loop cooling system.",
          "source_url": "https://www.azfamily.com/2026/09/08/pinal-county-rejects-data-center-despite-developers-concessions/",
          "source_tier": 4
        },
        {
          "status": "cancelled",
          "effective_at": "2026-09-08",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-08",
          "summary": "Vermaland proposed building 59 buildings and two gas fired power plants on 3,300 acres south of Eloy.",
          "source_url": "https://www.azfamily.com/2026/09/08/pinal-county-rejects-data-center-despite-developers-concessions/",
          "source_tier": 4
        },
        {
          "status": "rumored",
          "effective_at": "2026-08-26",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-08-26",
          "summary": "Developer reduced proposal from 59 buildings to 11 with two gas fired power plants planned",
          "source_url": "https://www.azfamily.com/video/2026/08/27/pinal-county-blocks-data-center-near-eloy-what-happens-now/",
          "source_tier": 4
        },
        {
          "status": "rumored",
          "effective_at": "2026-08-25",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-08-25",
          "summary": "A data center is proposed near Eloy and Picacho Peak in Pinal County, Arizona",
          "source_url": "https://www.azfamily.com/video/2026/08/26/why-pinal-county-residents-are-fighting-proposed-data-center/",
          "source_tier": 4
        }
      ]
    }
  ]
}