  "license": "CC BY-NC 4.0",
  "license_url": "https://creativecommons.org/licenses/by-nc/4.0/",
  "attribution": "Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0. Link to the specific record page where possible.",
  "source": "https://datacenterrecord.org/projects/terawulf-lake-hawkeye-lansing-ny",
  "retrieved_at": "2026-10-28T05:26:09.750Z",
  "count": 1,
  "projects": [
    {
      "slug": "terawulf-lake-hawkeye-lansing-ny",
      "name": "TeraWulf Cayuga Lake High Performance Computing Data Center Campus",
      "summary": "TeraWulf is constructing a 300 MW, 3 building high performance computing and AI data center campus at the former Cayuga Generating Station site on Cayuga Lake in Lansing, Tompkins County, New York.",
      "state": "NY",
      "city": "Lansing",
      "county": "Tompkins County",
      "status": "under_construction",
      "developer": "TeraWulf",
      "capacity_mw": 300,
      "latitude": 42.6025,
      "longitude": -76.6342,
      "location_precision": "address",
      "location_source": "https://www.terawulf.com/",
      "location_verified_at": null,
      "coordinate_source": "Tompkins County Parcel Viewer / TeraWulf Cayuga SEC Filing",
      "location_last_verified": null,
      "site_address": "2282 Fire Lane 1 (2282 Ridge Road), Lansing, NY 14882",
      "site_address_source_url": "https://www.terawulf.com/",
      "published": "2026-09-28",
      "last_verified": "2026-10-27",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 3,
      "buildings_basis": "operator page",
      "buildings_source_url": "https://www.terawulf.com/",
      "buildings_verified_at": "2026-10-27",
      "record_url": "https://datacenterrecord.org/projects/terawulf-lake-hawkeye-lansing-ny",
      "sources": [
        {
          "title": "Proposed data centers dividing New Yorkers - Spectrum News",
          "url": "https://spectrumlocalnews.com/nys/central-ny/environment/2026/07/07/proposed-data-centers-divide-new-yorkers",
          "publisher": "Spectrum News",
          "date": "2026-08-04",
          "source_tier": 1
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "proposed",
          "effective_at": "2026-08-04",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "TeraWulf proposes to convert an abandoned coal fired power plant near Cayuga Lake in Lansing into a 300 MW data center, facing lawsuits over environmental concerns.",
          "source_url": "https://spectrumlocalnews.com/nys/central-ny/environment/2026/07/07/proposed-data-centers-divide-new-yorkers",
          "source_tier": 1
        }
      ]
    }
  ]
}