  "license": "CC BY-NC 4.0",
  "license_url": "https://creativecommons.org/licenses/by-nc/4.0/",
  "attribution": "Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0. Link to the specific record page where possible.",
  "source": "https://datacenterrecord.org/projects/microsoft-palmetto-data-center-ga",
  "retrieved_at": "2026-10-27T01:47:33.873Z",
  "count": 1,
  "projects": [
    {
      "slug": "microsoft-palmetto-data-center-ga",
      "name": "Microsoft Palmetto Data Center (CCO06)",
      "summary": "Microsoft acquired nearly 21 acres adjacent to its existing Palmetto data center campus in south Fulton County for $6 million to support ongoing data center construction, and later purchased additional land near Atlanta.",
      "state": "GA",
      "city": "Palmetto",
      "county": "Fulton County",
      "status": "operational",
      "developer": "Microsoft",
      "capacity_mw": null,
      "latitude": 33.522969,
      "longitude": -84.631305,
      "location_precision": "permit_point",
      "location_source": "https://echo.epa.gov/detailed-facility-report?fid=110071963150",
      "location_verified_at": "2026-10-06",
      "coordinate_source": "EPA ECHO Detailed Facility Report 110071963150 and Georgia DCA DRI #3463",
      "location_last_verified": "2026-10-06",
      "site_address": "NW Corner of Johnson and Williams Rd, Palmetto, GA 30268",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110071963150",
      "published": "2026-10-21",
      "last_verified": "2026-10-26",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "state_permit_status": null,
      "state_permit_status_source_url": null,
      "state_permit_status_disclosed_as": "not_disclosed",
      "state_permit_status_as_of": null,
      "state_permit_status_last_verified": null,
      "buildings": 2,
      "buildings_basis": "permit",
      "buildings_source_url": "https://apps.dca.ga.gov/DRI/AdditionalForm.aspx?driid=3463",
      "buildings_verified_at": "2026-10-26",
      "record_url": "https://datacenterrecord.org/projects/microsoft-palmetto-data-center-ga",
      "sources": [
        {
          "title": "Microsoft pays $6M for land to expand data center south of Atlanta - AJC.com",
          "url": "https://www.ajc.com/news/business/microsoft-buys-land-for-expansion-of-fulton-county-data-center/WMEP3QOMDVDCXNLE3XM7MYMEBM/",
          "publisher": "AJC.com",
          "date": "2024-03-04",
          "source_tier": 1
        },
        {
          "title": "EPA ECHO detailed facility report: Microsoft Data Center (CCO06)",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110071963150",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        },
        {
          "title": "News | Microsoft Buys More Land Near Atlanta As It Expands National Data Center Footprint - CoStar",
          "url": "https://www.costar.com/article/1621439095?utm_source=newsletter%2CActiveCampaign&utm_medium=email%2Cemail&utm_campaign=personalized%2CJKAM+Newsletter+May+22%2C+2024&utm_content=p10%2CYour+Invitation+to+Invest+in+Atlanta+s+Most+Promising+Real+Estate%F0%9F%8F%A1&t=eyJhbGciOiJIUzI1NiIsInR5cCI6IkpXVCJ9.eyJjb250YWN0SWQiOiIxODcwNTQ2NTEiLCJjdWx0dXJlQ29kZSI6ImVuLVVTIiwiaWF0IjoxNzE2MjE4OTExfQ.DqVPhQUJSZIP7zo_IRFIKJau6CElYeraDY5Gx-KiZ6s",
          "publisher": "CoStar",
          "date": "2024-05-17",
          "source_tier": 1
        },
        {
          "title": "Georgia Department of Community Affairs: DRI Filing #3463 (Microsoft CCO06 Data Center, Palmetto, Fulton County)",
          "url": "https://apps.dca.ga.gov/DRI/AdditionalForm.aspx?driid=3463",
          "publisher": "Georgia Department of Community Affairs",
          "date": null,
          "source_tier": 1
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "under_construction",
          "effective_at": "2024-03-04",
          "date_basis": "content",
          "date_precision": "day",
          "planned": false,
          "source_date": null,
          "summary": "Microsoft acquired nearly 21 acres adjacent to its existing Palmetto data center campus in south Fulton County for $6 million to support ongoing data center construction, and later purchased additional land near Atlanta.",
          "source_url": "https://www.ajc.com/news/business/microsoft-buys-land-for-expansion-of-fulton-county-data-center/WMEP3QOMDVDCXNLE3XM7MYMEBM/",
          "source_tier": 1
        }
      ]
    }
  ]
}